1613 W 76TH ST 90047
Certificate Information: 1613 W 76TH ST 90047
- Application / Permit
- 24014-20000-05331
- Plan Check / Job No.
- B24VN24668
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND ADD 18'-9" x 10'-5" ALUMINUM OPEN TRELLIS PER ICC-ESR 4436
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Current Status
- Issued on 2/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2024 | JESSE ARELLANO |
| Corrections Issued | 12/12/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 12/17/2024 | APPLICANT |
| Applicant returned to address corrections | 2/21/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 2/25/2025 | ANGELICA MARTINEZ |
| Issued | 2/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2025 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 1/14/2025 | JUSTIN BICOL |
| Construction near power lines | Cleared | 2/14/2025 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 2/19/2025 | JUSTIN BICOL |
Contact Information
| Contractor | California Green Energy; Lic. No.: 896465-B | 17000 VENTURA BLVD STE 203 ENCINO, CA 91316 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/3/2025 | Partial Approval | JOHN QUINTANILLA |
| Sewer | 4/3/2025 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 4/3/2025 | Partial Approval | JOHN QUINTANILLA |
| Sewer | 4/7/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 4/7/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/17/2025 | Partial Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/17/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 4/17/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/17/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/23/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/23/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 4/23/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 4/23/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 4/23/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 4/25/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 5/2/2025 | Approved | JOHN QUINTANILLA |
| Shower Pan | 5/2/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 6/17/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 6/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 6/17/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 6/17/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 6/20/2025 | Approved | LUIS CASTRO |
| Final | 6/26/2025 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Final | 6/26/2025 | Approved | JOHN QUINTANILLA |