7900 W ELLENBOGEN ST 91040

Certificate Information: 7900 W ELLENBOGEN ST 91040

Application / Permit
24014-20000-05325
Plan Check / Job No.
B24VN24639
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN- Legalize un-permitted 8' X 15' storage room and 10' X 20' attached patio.
Permit Issued
Issued on 1/12/2025
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2024 APPLICANT
Assigned to Plan Check Engineer 12/18/2024 ARAMIK SHAHMIRZAIAN
Corrections Issued 12/19/2024 ARAMIK SHAHMIRZAIAN
Plan Check Approved 1/10/2025 ARAMIK SHAHMIRZAIAN
Issued 1/12/2025 APPLICANT
CofO in Progress 9/4/2025 WILLIAM WREN
CofO Issued 9/18/2025 RUBEN SALAS
Permit Finaled 9/18/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/27/2024 CHARLES POWELL
Roof/Waste drainage to street Cleared 12/29/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/6/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Hakobyan,, Sevak; Lic. No.: C96829 10238 LANGMUIR AVENUE      SUNLAND, CA 91040

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Order to Comply 3/11/2025 Not Required WILLIAM WREN
Pre-Inspection 3/11/2025 Not Ready for Inspection WILLIAM WREN
Pre-Inspection 3/20/2025 Approved FELIPE PENICHE
Pre-Inspection 5/8/2025 Corrections Issued WILLIAM WREN
Excavation/Setback/Form/Re-Bar 6/10/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/25/2025 Partial Approval WILLIAM WREN
Drywall Nailing 6/25/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 6/25/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/3/2025 Approved WILLIAM WREN
Drywall Nailing 7/3/2025 Approved WILLIAM WREN
Final 7/3/2025 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 7/3/2025 Approved WILLIAM WREN
Green Building Final 7/3/2025 Approved WILLIAM WREN
Green Building Rough 7/3/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Approved WILLIAM WREN
Smoke Detectors 7/3/2025 Not Ready for Inspection WILLIAM WREN
Wood Frame 7/3/2025 Approved WILLIAM WREN
Final 8/12/2025 OK to Issue CofO WILLIAM WREN
Smoke Detectors 8/12/2025 Approved WILLIAM WREN