15030 W MARLIN PL 91405
Certificate Information: 15030 W MARLIN PL 91405
- Application / Permit
- 24014-20000-05316
- Plan Check / Job No.
- B24VN24589
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Garage remodel addition - demolish existing rec room and deck on second floor and replace with new ADU on top of existing garage. 1 bedroom 1 bath over two car garage with new deck.
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Current Status
- CofO in Progress on 2/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | JOE VO |
| Corrections Issued | 12/22/2024 | JOE VO |
| Quality Review Completed | 12/26/2024 | GARO TELMI |
| Plan Check Approved | 4/1/2025 | JOE VO |
| Issued | 5/7/2025 | APPLICANT |
| CofO in Progress | 2/5/2026 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 2/25/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 2/28/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | J Z J B Cnst Inv; Lic. No.: 1013600-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/11/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/13/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/18/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Corrections Issued | RYAN SALAZAR |
| HVAC-Rough | 8/18/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/18/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Approved | LOUIS ESCOTO |
| Insulation | 8/28/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| Interior/Exterior Lathing | 8/28/2025 | Partial Approval | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/2/2025 | Approved | RYAN SALAZAR |
| Insulation | 9/2/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/15/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 9/15/2025 | Approved | LOUIS ESCOTO |
| Sewer | 11/19/2025 | Conditional Approval | MISAEL ESPARZA |
| Underground Mechanical | 11/19/2025 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/27/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 1/27/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 1/27/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 1/27/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 1/27/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 1/27/2026 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 2/4/2026 | Approved | JAVIER RAMOS JR |
| Final | 2/4/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 2/4/2026 | Not Required | JAVIER RAMOS JR |