7757 N LOUISE AVE 91325

Certificate Information: 7757 N LOUISE AVE 91325

Application / Permit
24014-20000-05305
Plan Check / Job No.
B24VN22926
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN NEW ADDITION TO (E) SFD 2 OF 2
Permit Issued
Issued on 5/13/2025
Issuing Office
Current Status
CofO Issued on 10/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 KHUONG TRUONG
Corrections Issued 12/3/2024 KHUONG TRUONG
Quality Review Completed 12/6/2024 GARO TELMI
Applicant returned to address corrections 2/5/2025 KHUONG TRUONG
Plan Check Approved 2/14/2025 KHUONG TRUONG
Issued 5/13/2025 APPLICANT
CofO in Progress 10/27/2025 GAREN HAYRAPETYAN
Permit Finaled 10/29/2025 RUBEN SALAS
CofO Issued 10/29/2025 RUBEN SALAS
Permit Finaled 10/29/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/29/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/2/2025 RYAN CASTRO
Trees in Parkway Cleared 1/29/2025 MIGUEL ORNELAS

Contact Information

Architect Sturgill,, Ben Curtis; Lic. No.: NA23174       ,
Contractor Warren Development Llc; Lic. No.: 1098736-B       ,
Engineer Simonian,, Ara; Lic. No.: NA37208       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/3/2025 Conditional Approval JOAQUIN GREENOUGH
Underground Mechanical 6/5/2025 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/9/2025 Not Ready for Inspection SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 6/11/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 6/30/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 7/1/2025 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 7/10/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 7/28/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Corrections Issued SALVADOR MARTINEZ
Shower Pan 7/28/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 7/31/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 7/31/2025 Approved GAREN HAYRAPETYAN
Wood Frame 7/31/2025 Approved GAREN HAYRAPETYAN
Insulation 8/5/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 8/5/2025 Partial Approval NICHOLAS TROWBRIDGE
Shower Pan 8/5/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 8/7/2025 Approved JAVIER RAMOS JR
Drywall Nailing 8/11/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 9/26/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 10/23/2025 Approved GAREN HAYRAPETYAN
Final 10/23/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 10/23/2025 Approved GAREN HAYRAPETYAN
Green Building Final 10/23/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 10/23/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 10/23/2025 Corrections Issued GAREN HAYRAPETYAN
Final 10/27/2025 OK to Issue CofO GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/27/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 10/27/2025 Approved GAREN HAYRAPETYAN