7757 N LOUISE AVE 91325
Certificate Information: 7757 N LOUISE AVE 91325
- Application / Permit
- 24014-20000-05305
- Plan Check / Job No.
- B24VN22926
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN NEW ADDITION TO (E) SFD 2 OF 2
- Permit Issued
- Issued on 5/13/2025
- Issuing Office
- Current Status
- CofO Issued on 10/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | KHUONG TRUONG |
| Corrections Issued | 12/3/2024 | KHUONG TRUONG |
| Quality Review Completed | 12/6/2024 | GARO TELMI |
| Applicant returned to address corrections | 2/5/2025 | KHUONG TRUONG |
| Plan Check Approved | 2/14/2025 | KHUONG TRUONG |
| Issued | 5/13/2025 | APPLICANT |
| CofO in Progress | 10/27/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 10/29/2025 | RUBEN SALAS |
| CofO Issued | 10/29/2025 | RUBEN SALAS |
| Permit Finaled | 10/29/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/29/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2025 | RYAN CASTRO |
| Trees in Parkway | Cleared | 1/29/2025 | MIGUEL ORNELAS |
Contact Information
| Architect | Sturgill,, Ben Curtis; Lic. No.: NA23174 | , |
| Contractor | Warren Development Llc; Lic. No.: 1098736-B | , |
| Engineer | Simonian,, Ara; Lic. No.: NA37208 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/3/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/5/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/9/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 6/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 6/30/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 7/1/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 7/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 7/28/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 7/31/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 7/31/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 7/31/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 8/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 8/5/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Shower Pan | 8/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 8/7/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 8/11/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 9/26/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/23/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 10/23/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 10/23/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 10/23/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/23/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 10/27/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/27/2025 | Approved | GAREN HAYRAPETYAN |