13735 W CHASE ST 91331
Certificate Information: 13735 W CHASE ST 91331
- Application / Permit
- 24014-20000-05267
- Plan Check / Job No.
- B24VN24380
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Addition to Ex. 2-Car Garage and convert to ADU (846 S.F.) per ordinance
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- Issued on 6/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2024 | NGHI SU |
| Corrections Issued | 12/12/2024 | NGHI SU |
| Plan Check Approved | 6/25/2025 | NGHI SU |
| Issued | 6/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/17/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 3/4/2025 | GEVORK KARAPETYAN |
| Roof/Waste drainage to street | Cleared | 3/15/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shmeit,, Ayman Ivan; Lic. No.: C93325 | 16905 ARMDORE AVE BELLFLOWER, CA 90706 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/30/2025 | No Access for Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 11/4/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 11/4/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/29/2026 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/29/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 1/29/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/2/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/2/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/2/2026 | Approved | VINCENT HANLEY |
| Deputy Wood Construction | 2/3/2026 | Conditional Approval | RAUL OLAGI |
| Insulation | 2/18/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/18/2026 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 2/26/2026 | Approved | VINCENT HANLEY |
| Shower Pan | 3/25/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/1/2026 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 6/2/2026 | Approved | OGANES TARAKHCHYAN |