4645 N WESTCHESTER DR 91364
Certificate Information: 4645 N WESTCHESTER DR 91364
- Application / Permit
- 24014-20000-05263
- Plan Check / Job No.
- B24VN24368
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ENCLOSURE BELOW (E) PATIO COVER TO ENLARGE KITCHEN AND DINING AREA TO (E) 2-STORY SFD PER ENGINEERING
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Current Status
- CofO Corrected on 3/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | ALFRED RAMIREZ |
| Corrections Issued | 12/16/2024 | ALFRED RAMIREZ |
| Building Plans Picked Up | 1/6/2025 | APPLICANT |
| Quality Review Completed | 1/14/2025 | STEVEN KIM |
| Plan Check Approved | 1/28/2025 | ALFRED RAMIREZ |
| Issued | 1/28/2025 | APPLICANT |
| CofO in Progress | 3/23/2026 | HENRY KIM |
| CofO Issued-Status Void | 3/26/2026 | JOHN JANSON |
| Permit Finaled-Status Void | 3/26/2026 | JOHN JANSON |
| Re-Activate Permit | 3/27/2026 | JOHN JANSON |
| Permit Finaled | 3/27/2026 | JOHN JANSON |
| CofO Corrected | 3/27/2026 | JOHN JANSON |
| Permit Finaled | 3/27/2026 | JOHN JANSON |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 12/26/2024 | ALEX VELA |
| ZI | Cleared | 12/26/2024 | ALEX VELA |
| Grading Pre-Inspection | Cleared | 12/26/2024 | CHARLES POWELL |
Contact Information
| Contractor | Ivy Green Construction; Lic. No.: 1014647-B | 14537 VENTURA BLVD SHERMAN OAKS, CA 91403 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16000 VENTURA BLVD., PH 1203 ENCINO, CA 91436 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/31/2025 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/16/2025 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 4/29/2025 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Rough | 5/1/2025 | Partial Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/21/2025 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 5/21/2025 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 5/29/2025 | Corrections Issued | JOHN COLEMAN |
| Shower Pan | 5/29/2025 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 6/6/2025 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 6/16/2025 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 7/1/2025 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 7/1/2025 | Partial Inspection | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Partial Approval | HENRY KIM |
| Interior/Exterior Lathing | 7/15/2025 | Partial Approval | HENRY KIM |
| Special/Order Compliance | 7/15/2025 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/17/2025 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2025 | Partial Approval | HENRY KIM |
| Special/Order Compliance | 7/17/2025 | Partial Inspection | SEAN WIRCH |
| ELECTRICAL-Rough | 7/24/2025 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 7/24/2025 | Partial Inspection | SEAN WIRCH |
| ELECTRICAL-Rough | 8/1/2025 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Partial Approval | HENRY KIM |
| Special/Order Compliance | 8/1/2025 | Partial Inspection | SEAN WIRCH |
| HVAC-Rough | 8/6/2025 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 8/6/2025 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/19/2025 | Corrections Issued | HENRY KIM |
| HVAC-Final | 8/19/2025 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 8/19/2025 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 8/19/2025 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/22/2025 | Corrections Issued | HENRY KIM |
| Insulation | 8/22/2025 | Partial Approval | HENRY KIM |
| Special/Order Compliance | 8/22/2025 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 9/2/2025 | Corrections Issued | HENRY KIM |
| Drywall Nailing | 9/2/2025 | Partial Approval | HENRY KIM |
| Insulation | 9/2/2025 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 9/2/2025 | Partial Approval | HENRY KIM |
| Special/Order Compliance | 9/2/2025 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | HENRY KIM |
| Drywall Nailing | 10/24/2025 | Approved | HENRY KIM |
| HVAC-Rough | 10/24/2025 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 10/24/2025 | Approved | HENRY KIM |
| Special/Order Compliance | 10/24/2025 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 10/24/2025 | Partial Inspection | ROBERT GOLD |
| Underground Mechanical | 11/7/2025 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 2/12/2026 | Corrections Issued | HENRY KIM |
| Final | 2/12/2026 | Corrections Issued | HENRY KIM |
| Gas Test | 2/12/2026 | Corrections Issued | HENRY KIM |
| HVAC-Final | 2/12/2026 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 2/12/2026 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 2/12/2026 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 2/12/2026 | Partial Inspection | ROBERT GOLD |
| ELECTRICAL-Final | 3/3/2026 | Corrections Issued | HENRY KIM |
| Final | 3/3/2026 | Corrections Issued | HENRY KIM |
| Gas Test | 3/3/2026 | Corrections Issued | HENRY KIM |
| HVAC-Final | 3/3/2026 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 3/3/2026 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 3/3/2026 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 3/3/2026 | Approved | HENRY KIM |
| Special/Order Compliance | 3/3/2026 | Partial Inspection | ROBERT GOLD |
| ELECTRICAL-Final | 3/11/2026 | Approved | HENRY KIM |
| Final | 3/11/2026 | Corrections Issued | HENRY KIM |
| Gas Test | 3/11/2026 | Approved | HENRY KIM |
| HVAC-Final | 3/11/2026 | Approved | HENRY KIM |
| PLUMBING-Final | 3/11/2026 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | HENRY KIM |
| Special/Order Compliance | 3/11/2026 | Partial Inspection | ROBERT GOLD |
| Final | 3/23/2026 | OK to Issue CofO | HENRY KIM |