11013-11015 N NOBLE AVE 91345
Certificate Information: 11013-11015 N NOBLE AVE 91345
- Application / Permit
- 24014-20000-05260
- Plan Check / Job No.
- B24VN24353
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- <ePLAN> ADDITION & CONVERSION OF A 2-CAR GARAGE INTO A 20'7"X23'6" 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 4/27/2025
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | MARVEL DELACRUZ |
| Corrections Issued | 12/8/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 12/11/2024 | JASON HEALEY |
| Applicant returned to address corrections | 3/27/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 4/22/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 4/25/2025 | INTERNET PERMIT |
| Issued | 4/27/2025 | APPLICANT |
| CofO in Progress | 3/13/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 5/19/2026 | RUBEN SALAS |
| CofO Issued | 5/19/2026 | RUBEN SALAS |
| Permit Finaled | 5/19/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 3/14/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 3/15/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/21/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 7/22/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 7/22/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 7/23/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 7/25/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 7/25/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 8/11/2025 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/11/2025 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/13/2025 | Approved | RAUL OLAGI |
| Special/Order Compliance | 8/13/2025 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/6/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 11/6/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/6/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/24/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 11/24/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 11/24/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 11/26/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 11/26/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/5/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/5/2025 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 12/5/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/18/2025 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 12/18/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/13/2026 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 2/11/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/27/2026 | Approved | JENNIFER RABUCHIN |
| Final | 2/27/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/27/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 2/27/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/4/2026 | Approved | JENNIFER RABUCHIN |
| Final | 3/4/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 3/4/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/4/2026 | Approved | JENNIFER RABUCHIN |