14649 W LEADWELL ST 91405

Certificate Information: 14649 W LEADWELL ST 91405

Application / Permit
24014-20000-05227
Plan Check / Job No.
B24VN24147
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET GARAGE AND (N) 9' X 14' ADDITION AND CONVERT ENTIRE BUILDING TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP SEE COMMENTS
Permit Issued
Issued on 12/6/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2024 APPLICANT
Assigned to Plan Check Engineer 12/3/2024 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/3/2024 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 12/3/2024 APPLICANT
Plan Check Approved 12/6/2024 YAQUB MIRZA
Issued 12/6/2024 APPLICANT
CofO in Progress 6/27/2025 VINCENT HANLEY
Permit Finaled 7/22/2025 RUBEN SALAS
CofO Issued 7/22/2025 RUBEN SALAS
Permit Finaled 7/22/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/5/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/5/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/5/2024 LEE GUILBEAUX
Sewer availability Cleared 12/5/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/5/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/26/2025 Partial Approval VINCENT HANLEY
Sewer 2/26/2025 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 2/27/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/4/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 3/4/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/19/2025 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 3/19/2025 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 4/11/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 4/21/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Partial Approval VINCENT HANLEY
HVAC-Rough 4/21/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/21/2025 Approved VINCENT HANLEY
Insulation 4/28/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/2/2025 Approved VINCENT HANLEY
Drywall Nailing 5/2/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Approved VINCENT HANLEY
Green Building Rough 5/2/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 6/17/2025 Corrections Issued VINCENT HANLEY
Final 6/17/2025 Corrections Issued VINCENT HANLEY
Green Building Final 6/17/2025 Approved VINCENT HANLEY
HVAC-Final 6/17/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Final 6/17/2025 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/17/2025 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 6/17/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 6/26/2025 Approved VINCENT HANLEY
Final 6/26/2025 OK to Issue CofO VINCENT HANLEY
HVAC-Final 6/26/2025 Approved VINCENT HANLEY
PLUMBING-Final 6/26/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved VINCENT HANLEY