6500-6502 N GENTRY AVE 91606

Certificate Information: 6500-6502 N GENTRY AVE 91606

Application / Permit
24014-20000-05222
Plan Check / Job No.
B24VN24110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: ADDITION TO (E) SINGLE FAMILY DWELLING TO CREATE A 1-STORY DUPLEX WITH ATTACHED GARAGE PER SENATE BILL 9 TWO UNIT DEVELOPMENT. 13D FIRE SPRINKLER THROUGH-OUT.
Permit Issued
Issued on 4/8/2025
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 DANIEL YIP
Corrections Issued 12/7/2024 DANIEL YIP
Quality Review Completed 12/9/2024 GARO TELMI
Applicant returned to address corrections 1/16/2025 DANIEL YIP
Applicant returned to address corrections 3/11/2025 DANIEL YIP
Plan Check Approved 3/26/2025 DANIEL YIP
Issued 4/8/2025 APPLICANT
CofO in Progress 2/17/2026 JOSE AVILA
Permit Finaled 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/2/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/7/2025 RYAN CASTRO
Sewer availability Cleared 1/7/2025 RYAN CASTRO
Trees in Parkway Cleared 2/20/2025 MIGUEL ORNELAS
Roof/Waste drainage to street Cleared 3/18/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/22/2025 Partial Approval JAVIER RAMOS JR
Pre-Inspection 5/22/2025 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 5/27/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 6/3/2025 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 6/5/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/5/2025 Approved JOSE AVILA
Wood Frame 6/26/2025 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Approved JOSE AVILA
Interior/Exterior Lathing 8/4/2025 Partial Approval JOSE AVILA
Shower Pan 8/4/2025 Approved JOSE AVILA
ELECTRICAL-Rough 8/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 8/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 9/2/2025 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 9/16/2025 Approved JOSE AVILA
ELECTRICAL-Rough 9/16/2025 Approved JOSE AVILA
HVAC-Rough 9/16/2025 Approved JOSE AVILA
PLUMBING-Rough 9/16/2025 Approved JOSE AVILA
Insulation 9/18/2025 Approved JOSE AVILA
Drywall Nailing 9/22/2025 Approved JOSE AVILA
Green Building Rough 9/22/2025 Approved JOSE AVILA
ELECTRICAL-Final 10/29/2025 Corrections Issued JOSE AVILA
Final 10/29/2025 Corrections Issued JOSE AVILA
Green Building Final 10/29/2025 Approved JOSE AVILA
HVAC-Final 10/29/2025 Approved JOSE AVILA
PLUMBING-Final 10/29/2025 Not Ready for Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 10/29/2025 Approved JOSE AVILA
ELECTRICAL-Final 11/4/2025 Approved JOSE AVILA
HVAC-Final 11/4/2025 Approved JOSE AVILA
PLUMBING-Final 11/4/2025 Approved JOSE AVILA
Final 2/17/2026 OK to Issue CofO JOSE AVILA