5083 N NESTLE AVE 91356

Certificate Information: 5083 N NESTLE AVE 91356

Application / Permit
24014-20000-05219
Plan Check / Job No.
B24VN24097
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 3'-3" X 15'-6" TO FRONT OF SINGLE FAMILY DWELLING; CONVERT 3'-7" X 10'-6" PORCH TO PART OF SFD; REFRAME ENTIRE ROOF
Permit Issued
Issued on 2/12/2025
Issuing Office
Valley
Current Status
Issued on 2/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/25/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 SELLA BENYAMIN
Corrections Issued 12/13/2024 SELLA BENYAMIN
Quality Review Completed 12/13/2024 STEVEN KIM
Building Plans Picked Up 12/16/2024 APPLICANT
Plan Check Approved 2/11/2025 SELLA BENYAMIN
Issued 2/12/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/18/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 12/18/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/18/2024 BIAINA HARITUNIAN
Watercourse Cleared 12/19/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/20/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 2/20/2025 Corrections Issued JOHN KIDWELL
PLUMBING-Rough 2/20/2025 Partial Approval JOHN KIDWELL
Sewer 2/20/2025 Approved JOHN KIDWELL
Footing/Foundation/Slab 3/3/2025 Approved JOHN KIDWELL
Deputy Drilled-In Anchors 5/20/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval JOHN KIDWELL
PLUMBING-Rough 5/21/2025 Partial Approval JOHN KIDWELL
Sewer 5/21/2025 Approved JOHN KIDWELL
Deputy Drilled-In Anchors 5/27/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 6/4/2025 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Partial Approval JOHN KIDWELL
HVAC-Final 6/4/2025 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 6/4/2025 Partial Approval JOHN KIDWELL
PLUMBING-Rough 6/4/2025 Partial Approval JOHN KIDWELL
Wood Frame 6/4/2025 Partial Approval JOHN KIDWELL
Gas Test 6/26/2025 Partial Inspection HENRY KIM
Interior/Exterior Lathing 6/26/2025 Partial Approval HENRY KIM
PLUMBING-Rough 6/26/2025 Partial Approval HENRY KIM
Underground Mechanical 6/26/2025 Partial Approval HENRY KIM
ELECTRICAL-Rough 7/10/2025 Approved JOHN KIDWELL
HVAC-Rough 7/10/2025 Approved JOHN KIDWELL
Insulation 7/17/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 7/17/2025 Partial Approval JOHN KIDWELL
Shower Pan 7/17/2025 Approved JOHN KIDWELL
Drywall Nailing 7/30/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 7/30/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 3/20/2026 Approved JOHN KIDWELL
ELECTRICAL-Final 3/20/2026 Approved JOHN KIDWELL
Final 3/20/2026 Corrections Issued JOHN KIDWELL
Green Building Final 3/20/2026 Approved JOHN KIDWELL
Green Building Rough 3/20/2026 Approved JOHN KIDWELL
PLUMBING-Final 3/20/2026 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Approved JOHN KIDWELL
Service/Power Release 3/20/2026 Approved JOHN KIDWELL
Smoke Detectors 3/20/2026 Approved JOHN KIDWELL