10306 N WOODWARD AVE 91040
Certificate Information: 10306 N WOODWARD AVE 91040
- Application / Permit
- 24014-20000-05214
- Plan Check / Job No.
- B24VN24081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE PORTION OF EX. DETACHED GARAGE. ADDITION TO AND CONVERT/ REFRAME ROOF OF GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(2).
- Permit Issued
- Issued on 4/2/2025
- Issuing Office
- Current Status
- CofO Issued on 1/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 12/4/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/5/2024 | APPLICANT |
| Plan Check Approved | 4/2/2025 | ROSENDO MEDINA |
| Issued | 4/2/2025 | APPLICANT |
| CofO in Progress | 12/24/2025 | DAVID ANDERSON |
| Permit Finaled | 1/23/2026 | RUBEN SALAS |
| CofO Issued | 1/23/2026 | RUBEN SALAS |
| Permit Finaled | 1/23/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/5/2024 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 1/28/2025 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/3/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/13/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 5/21/2025 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 5/21/2025 | Approved | DAVID MATSON |
| Deputy Drilled-In Anchors | 5/27/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/29/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/22/2025 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 7/22/2025 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 7/22/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 7/22/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/25/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 7/25/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 7/29/2025 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/29/2025 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/29/2025 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/1/2025 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 8/1/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/1/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/7/2025 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 8/7/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/7/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/12/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/12/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 8/12/2025 | Approved | DAVID ANDERSON |
| Insulation | 8/12/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/12/2025 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 8/19/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/19/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 8/21/2025 | Approved | WILLIAM WREN |
| Final | 12/16/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 12/16/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 12/16/2025 | Approved | DAVID ANDERSON |
| Final | 12/22/2025 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 12/22/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Approved | DAVID ANDERSON |