23236 W HATTERAS ST 91367
Certificate Information: 23236 W HATTERAS ST 91367
- Application / Permit
- 24014-20000-05206
- Plan Check / Job No.
- B24VN24016
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remove attached carport, convert detached garage to part of the SFD, and remove second story ALQ on top of the garage, and irregular shaped addition for new footprint of 133' x 48' Single Family Dwelling, with attached garage, and patio cover. NFPA 13D sprinkler required.
- Permit Issued
- Issued on 1/23/2025
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2024 | NAREG ATARIAN |
| Corrections Issued | 12/3/2024 | NAREG ATARIAN |
| Quality Review Completed | 12/4/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 12/5/2024 | APPLICANT |
| Applicant returned to address corrections | 12/12/2024 | NAREG ATARIAN |
| Plan Check Approved | 1/22/2025 | NAREG ATARIAN |
| Issued | 1/23/2025 | APPLICANT |
| CofO in Progress | 8/15/2025 | TROY SANDERS |
| No Progress | 10/27/2025 | ROBERT GOLD |
| CofO in Progress | 10/27/2025 | ROBERT GOLD |
| Permit Finaled | 12/30/2025 | JOHN JANSON |
| CofO Issued | 12/30/2025 | JOHN JANSON |
| Permit Finaled | 12/30/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/4/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 12/9/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 12/10/2024 | MANUEL TEJADA |
| GPI Written Notices | Cleared | 1/22/2025 | NAREG ATARIAN |
Contact Information
| Contractor | Jb Home Builders Co; Lic. No.: 619281-B | 6745 DARBY AVENUE RESEDA, CA 91335 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/20/2025 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 3/26/2025 | Approved | TROY SANDERS |
| Special/Order Compliance | 4/2/2025 | No Access for Inspection | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Partial Approval | TROY SANDERS |
| Special/Order Compliance | 4/7/2025 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/23/2025 | Approved | TROY SANDERS |
| Green Building Rough | 4/23/2025 | Not Ready for Inspection | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 4/23/2025 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/1/2025 | Approved | TROY SANDERS |
| Green Building Rough | 5/1/2025 | Approved | TROY SANDERS |
| Insulation | 5/1/2025 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/1/2025 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 5/7/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 6/6/2025 | Approved | TROY SANDERS |
| Service/Power Release | 6/6/2025 | Approved | TROY SANDERS |
| HVAC-Final | 6/9/2025 | Approved | TROY SANDERS |
| Final | 8/4/2025 | Corrections Issued | TROY SANDERS |
| Green Building Final | 8/4/2025 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/4/2025 | Approved | TROY SANDERS |
| Final | 8/14/2025 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/14/2025 | Approved | TROY SANDERS |
| Special/Order Compliance | 8/22/2025 | Partial Approval | TROY SANDERS |
| Special/Order Compliance | 10/24/2025 | Approved | TROY SANDERS |
| Special/Order Compliance | 11/3/2025 | Partial Inspection | ROBERT GOLD |
| Special/Order Compliance | 11/7/2025 | Corrections Issued | ROBERT GOLD |
| Pre-Inspection | 12/23/2025 | Partial Inspection | ROBERT GOLD |