22554-22556 W COVELLO ST 91307

Certificate Information: 22554-22556 W COVELLO ST 91307

Application / Permit
24014-20000-05196
Plan Check / Job No.
B24VN23943
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO SFD AND CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 12/17/2024
Issuing Office
Current Status
CofO Issued on 9/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 JEROME MAGAT PALMA
Corrections Issued 11/30/2024 JEROME MAGAT PALMA
Building Plans Picked Up 12/2/2024 APPLICANT
Plan Check Approved 12/17/2024 GURUNATH NESARAJAH
Issued 12/17/2024 APPLICANT
CofO in Progress 9/30/2025 JEFFREY HARTLINE
Permit Finaled 9/30/2025 MICHAEL PELHAM
CofO Issued 9/30/2025 MICHAEL PELHAM
Permit Finaled 9/30/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 12/6/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/6/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/6/2024 EDGAR ALCARAZ
Sewer availability Cleared 12/6/2024 EDGAR ALCARAZ

Contact Information

Contractor V Z V Builders & Home Improvement Inc; Lic. No.: 1014885-B 11856 BALBOA BOULEVARD #675      GRANADA HILLS, CA 91334
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2025 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/7/2025 Partial Approval JEFFREY HARTLINE
Footing/Foundation/Slab 1/7/2025 Partial Approval JEFFREY HARTLINE
Underground Mechanical 1/7/2025 Partial Approval JEFFREY HARTLINE
Footing/Foundation/Slab 2/11/2025 Corrections Issued JEFFREY HARTLINE
BUILDING-Rough-Frame 3/6/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 3/6/2025 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval JEFFREY HARTLINE
Green Building Rough 3/6/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 3/6/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 3/6/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 3/18/2025 Partial Approval JEFFREY HARTLINE
Green Building Rough 3/18/2025 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 3/18/2025 Partial Approval JEFFREY HARTLINE
Wood Frame 3/18/2025 Approved JEFFREY HARTLINE
Insulation 4/3/2025 Approved JEFFREY HARTLINE
Drywall Nailing 4/11/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/12/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 9/12/2025 Approved JEFFREY HARTLINE
Final 9/12/2025 OK to Issue CofO JEFFREY HARTLINE
Footing/Foundation/Slab 9/12/2025 Approved JEFFREY HARTLINE
Green Building Final 9/12/2025 Approved JEFFREY HARTLINE
Green Building Rough 9/12/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 9/12/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 9/12/2025 Approved JEFFREY HARTLINE