7329 N MASON AVE 91306
Certificate Information: 7329 N MASON AVE 91306
- Application / Permit
- 24014-20000-05195
- Plan Check / Job No.
- B24VN23938
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 3/11/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 11/30/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/3/2024 | APPLICANT |
| Applicant returned to address corrections | 2/18/2025 | ROSENDO MEDINA |
| Plan Check Approved | 3/11/2025 | ANGELICA MARTINEZ |
| Issued | 3/11/2025 | APPLICANT |
| CofO in Progress | 12/12/2025 | ROBERT GOLD |
| Permit Finaled | 12/17/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/17/2025 | MICHAEL PELHAM |
| CofO Issued | 12/17/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 12/24/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/24/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/24/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/27/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mao,, Yuqiao; Lic. No.: C90108 | 136 LOST HILLS IRVINE, CA 92618 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/23/2025 | Partial Approval | JUAN ALVARADO |
| Pre-Inspection | 4/23/2025 | Corrections Issued | JUAN ALVARADO |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 5/8/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 7/10/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 7/10/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/21/2025 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 8/21/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 8/21/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 8/21/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 8/21/2025 | Approved | ALEXANDER HANDY |
| Insulation | 9/25/2025 | Approved | ALEXANDER HANDY |
| Sewer | 9/25/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 9/25/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 10/1/2025 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 11/26/2025 | Approved | ROBERT GOLD |
| Final | 11/26/2025 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 11/26/2025 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 11/26/2025 | Approved | ROBERT GOLD |
| Final | 12/5/2025 | OK to Issue CofO | ROBERT GOLD |