7046 N ALCOVE AVE 91605

Certificate Information: 7046 N ALCOVE AVE 91605

Application / Permit
24014-20000-05193
Plan Check / Job No.
B24VN23916
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION (42'-4" X 21'- 1") TO THE (E) SFD AND ADDITION OF (7'-6"' X4'-3") COVERED PORCH TO WEST OF (E) SFD UNIT. *****NFPA 13D FIRE SPRINKLERD THROUGHOUT
Permit Issued
Issued on 12/30/2024
Issuing Office
Current Status
CofO Issued on 8/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 EDWARD MEHRABIAN
Corrections Issued 12/5/2024 EDWARD MEHRABIAN
Quality Review Completed 12/11/2024 OMID HEDAYAT
Plan Check Approved 12/26/2024 EDWARD MEHRABIAN
Issued 12/30/2024 APPLICANT
CofO in Progress 8/4/2025 OGANES TARAKHCHYAN
CofO Issued 8/20/2025 RUBEN SALAS
Permit Finaled 8/20/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/18/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/19/2024 EDGAR ALCARAZ
Sewer availability Cleared 12/19/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/6/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 2/7/2025 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 2/26/2025 Partial Approval GAREN HAYRAPETYAN
Insulation 3/19/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 4/21/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/5/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 5/5/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 5/5/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 5/5/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 5/5/2025 Approved GAREN HAYRAPETYAN
Gas Test 5/8/2025 Partial Approval OGANES TARAKHCHYAN
Sewer 5/8/2025 Approved OGANES TARAKHCHYAN
Underground Mechanical 5/8/2025 Approved OGANES TARAKHCHYAN
Insulation 5/12/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/14/2025 Partial Approval OGANES TARAKHCHYAN
Shower Pan 5/19/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 5/21/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 5/22/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 5/22/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/5/2025 Approved DAVID MATSON
Footing/Foundation/Slab 7/30/2025 Approved GAREN HAYRAPETYAN
Green Building Final 7/30/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 7/30/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 8/1/2025 Approved OGANES TARAKHCHYAN
Final 8/1/2025 OK to Issue CofO OGANES TARAKHCHYAN
Gas Test 8/1/2025 Approved OGANES TARAKHCHYAN
HVAC-Final 8/1/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Final 8/1/2025 Approved OGANES TARAKHCHYAN
Service/Power Release 8/1/2025 Approved OGANES TARAKHCHYAN