7663 N SEDAN AVE 91304

Certificate Information: 7663 N SEDAN AVE 91304

Application / Permit
24014-20000-05189
Plan Check / Job No.
B24VN23881
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Add 9' x 14'-3 1/2" to (E)SFD and remodel. All Work Per Architect
Permit Issued
Issued on 12/9/2024
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 ARAMIK SHAHMIRZAIAN
Corrections Issued 11/28/2024 ARAMIK SHAHMIRZAIAN
Plan Check Approved 12/5/2024 ARAMIK SHAHMIRZAIAN
Issued 12/9/2024 APPLICANT
CofO in Progress 10/29/2025 CHRIS CHRISTENSEN
Permit Finaled 11/13/2025 JOHN JANSON
CofO Issued 11/13/2025 JOHN JANSON
Permit Finaled 11/13/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/2/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/4/2024 CARLOS AGUILERA
Sewer availability Cleared 12/4/2024 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/11/2024 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 12/13/2024 Approved JEFFREY HARTLINE
Underground Mechanical 12/13/2024 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 12/17/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Rough 1/17/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Partial Approval JEFFREY HARTLINE
HVAC-Rough 1/17/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 1/17/2025 Not Ready for Inspection JEFFREY HARTLINE
Shower Pan 1/17/2025 Approved JEFFREY HARTLINE
Deputy Wood Construction 1/21/2025 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/30/2025 Approved JEFFREY HARTLINE
Green Building Rough 1/30/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/30/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 1/30/2025 Approved JEFFREY HARTLINE
Insulation 2/3/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/7/2025 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 2/12/2025 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 5/14/2025 Conditional Approval HENRY KIM
ELECTRICAL-Final 10/21/2025 Approved CHRIS CHRISTENSEN
Final 10/21/2025 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/21/2025 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 10/21/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/21/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/21/2025 Approved CHRIS CHRISTENSEN
Final 10/28/2025 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 10/28/2025 Approved CHRIS CHRISTENSEN