15951 W LASSEN ST 91343

Certificate Information: 15951 W LASSEN ST 91343

Application / Permit
24014-20000-05162
Plan Check / Job No.
B24VN23660
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 2/4/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 JEROME MAGAT PALMA
Corrections Issued 11/26/2024 JEROME MAGAT PALMA
Building Plans Picked Up 12/2/2024 APPLICANT
Applicant returned to address corrections 12/13/2024 GIOVANNY CHAVEZ
Plan Check Approved 1/17/2025 GURUNATH NESARAJAH
Issued 2/4/2025 APPLICANT
CofO in Progress 5/8/2025 CHRISTOPHER ROJAS
Permit Finaled 5/12/2025 RUBEN SALAS
CofO Issued 5/12/2025 RUBEN SALAS
Permit Finaled 5/12/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/5/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/5/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/10/2024 CARLOS AGUILERA
Sewer availability Cleared 12/10/2024 CARLOS AGUILERA
Construction near power lines Cleared 1/9/2025 TINA MIRANDA
Grading Pre-Inspection Cleared 1/17/2025 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Azarbin,, Hamid; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 2/21/2025 Partial Approval JAVIER RAMOS JR
Sewer 2/21/2025 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 2/26/2025 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 2/26/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/12/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 3/17/2025 Approved JAVIER RAMOS JR
HVAC-Rough 3/17/2025 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 3/17/2025 Approved JAVIER RAMOS JR
Underground Mechanical 3/17/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 3/20/2025 Partial Approval JAVIER RAMOS JR
Green Building Rough 3/20/2025 Approved JAVIER RAMOS JR
HVAC-Rough 3/20/2025 Approved JAVIER RAMOS JR
Shower Pan 3/20/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/21/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 3/25/2025 Approved CHRISTOPHER ROJAS
Insulation 3/25/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 3/28/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 3/28/2025 Partial Approval MICHAEL CORTEZ
Interior/Exterior Lathing 4/2/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/25/2025 Approved CHRISTOPHER ROJAS
Gas Test 5/1/2025 Approved JENNIFER RABUCHIN
Green Building Final 5/1/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 5/1/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 5/1/2025 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 5/1/2025 Approved JENNIFER RABUCHIN
Final 5/7/2025 OK to Issue CofO CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/7/2025 Approved CHRISTOPHER ROJAS
Green Building Final 5/7/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 5/7/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 5/7/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 5/7/2025 Approved CHRISTOPHER ROJAS