7752 N ENSIGN AVE 91352
Certificate Information: 7752 N ENSIGN AVE 91352
- Application / Permit
- 24014-20000-05148
- Plan Check / Job No.
- B24VN23542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH ADDITION TO DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/13/2025
- Issuing Office
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2024 | CARLOS MONTES |
| Corrections Issued | 11/23/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 1/9/2025 | CARLOS MONTES |
| Applicant returned to address corrections | 1/15/2025 | ALEXANDER JOO |
| Plan Check Approved | 2/8/2025 | CARLOS MONTES |
| Issued | 2/13/2025 | APPLICANT |
| CofO in Progress | 3/3/2026 | MATTHEW NELSON |
| CofO Issued | 6/4/2026 | RUBEN SALAS |
| Permit Finaled | 6/4/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 1/6/2025 | GEVORK KARAPETYAN |
| Permit | Cleared | 1/10/2025 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 2/6/2025 | MIGUEL ORNELAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/18/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 3/18/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Excavation/Setback/Form/Re-Bar | 3/25/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/28/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 4/28/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 4/28/2025 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/15/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/15/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Wood Frame | 5/15/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/30/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 5/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Approved | MATTHEW NELSON |
| Insulation | 6/18/2025 | Corrections Issued | MATTHEW NELSON |
| Drywall Nailing | 7/9/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 9/5/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/16/2025 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/24/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 10/29/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 10/29/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 10/29/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/20/2025 | Approved | MATTHEW NELSON |
| Final | 11/20/2025 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/20/2025 | Approved | MATTHEW NELSON |
| Green Building Final | 11/20/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 11/20/2025 | Approved | MATTHEW NELSON |
| Final | 11/24/2025 | Corrections Issued | MATTHEW NELSON |
| Final | 3/2/2026 | OK to Issue CofO | MATTHEW NELSON |