5530 W GEER AVE 90016
Certificate Information: 5530 W GEER AVE 90016
- Application / Permit
- 24014-20000-05135
- Plan Check / Job No.
- B24VN23463
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 18'-2" X 4'-0" PORCH ADDITION & 18'-2" X 19-11"ADDITION TO (E) SFD.
- Permit Issued
- Issued on 11/27/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 11/25/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/26/2024 | APPLICANT |
| Issued | 11/27/2024 | APPLICANT |
| CofO in Progress | 10/17/2025 | WILLIAM SIERRA |
| Permit Finaled | 10/19/2025 | DEROLD HAUFF |
| CofO Issued | 10/19/2025 | DEROLD HAUFF |
| Permit Finaled | 10/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 11/26/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 11/26/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mansuri,, Mehran; Lic. No.: C78614 | 14944 HESBY ST SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/4/2024 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 12/4/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/29/2025 | Conditional Approval | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 1/29/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 1/29/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Rough | 1/29/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| PLUMBING-Rough | 1/29/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 2/5/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 2/5/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 2/5/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 2/5/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 2/5/2025 | Partial Inspection | ALEX COLIN |
| Drywall Nailing | 2/20/2025 | Approved | ARTHUR NEGRETE |
| Shower Pan | 2/20/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 2/24/2025 | Approved | ALEX COLIN |
| Shower Pan | 2/24/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 5/6/2025 | Partial Inspection | ARTHUR NEGRETE |
| Final | 6/4/2025 | Conditional Approval | ARTHUR NEGRETE |
| Green Building Final | 6/4/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 6/4/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 7/15/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 7/15/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 7/15/2025 | Approved | ARTHUR NEGRETE |
| Final | 7/17/2025 | Conditional Approval | ARTHUR NEGRETE |
| Final | 10/17/2025 | OK to Issue CofO | WILLIAM SIERRA |