7652 N LOUISE AVE 91406

Certificate Information: 7652 N LOUISE AVE 91406

Application / Permit
24014-20000-05107
Plan Check / Job No.
B24VN23292
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: 298 SF ADDITION TO (E) SFD
Permit Issued
Issued on 2/19/2025
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 LUISANGEL VALENZUELA
Corrections Issued 11/22/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/11/2025 LUISANGEL VALENZUELA
Plan Check Approved 2/18/2025 PINANK PATEL
Plan Check Approved 2/19/2025 PINANK PATEL
Issued 2/19/2025 APPLICANT
CofO in Progress 10/6/2025 GAREN HAYRAPETYAN
Permit Finaled 10/7/2025 RUBEN SALAS
CofO Issued 10/7/2025 RUBEN SALAS
Permit Finaled 10/7/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/3/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/10/2025 EDGAR ALCARAZ
Sewer availability Cleared 2/13/2025 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/21/2025 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 5/9/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/14/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/14/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/28/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/28/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 6/12/2025 Corrections Issued SALVADOR MARTINEZ
Deputy Wood Construction 7/10/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/11/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/18/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/18/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 8/21/2025 Approved GAREN HAYRAPETYAN
Wood Frame 8/21/2025 Approved GAREN HAYRAPETYAN
Insulation 8/25/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/25/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 8/25/2025 Approved JAVIER RAMOS JR
Drywall Nailing 9/2/2025 Approved LOUIS ESCOTO
Green Building Rough 9/2/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 9/2/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 10/1/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 10/1/2025 Approved GAREN HAYRAPETYAN
Final 10/1/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 10/1/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 10/1/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Final 10/1/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 10/1/2025 Corrections Issued GAREN HAYRAPETYAN
Final 10/6/2025 OK to Issue CofO GAREN HAYRAPETYAN
Smoke Detectors 10/6/2025 Approved GAREN HAYRAPETYAN