12507 W MIRANDA ST 91607
Certificate Information: 12507 W MIRANDA ST 91607
- Application / Permit
- 24014-20000-05075
- Plan Check / Job No.
- B24VN23033
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE ONE STORY ADDITION TO (E) SFD AND MAJOR REMODEL, LEAVING ONE WALL AT SIDE OF (E) GARAGE_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 3/15/2025
- Issuing Office
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | DAWN MC NULTY |
| Corrections Issued | 11/24/2024 | DAWN MC NULTY |
| Quality Review Completed | 11/27/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 1/9/2025 | DAWN MC NULTY |
| Applicant returned to address corrections | 2/21/2025 | DAWN MC NULTY |
| Applicant returned to address corrections | 3/5/2025 | DAWN MC NULTY |
| Applicant returned to address corrections | 3/7/2025 | DAWN MC NULTY |
| Plan Check Approved | 3/13/2025 | DAWN MC NULTY |
| Issued | 3/15/2025 | APPLICANT |
| CofO in Progress | 11/21/2025 | WAYNE REGESTER |
| No Progress | 3/14/2026 | RAUL OLAGI |
| CofO in Progress | 3/14/2026 | RAUL OLAGI |
| CofO Issued | 6/2/2026 | RUBEN SALAS |
| Permit Finaled | 6/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/10/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/11/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Susan Development And Construction Inc; Lic. No.: 1089492-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/23/2025 | Approved | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 5/29/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 5/29/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/9/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 6/9/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 6/12/2025 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Corrections Issued | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 7/7/2025 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 7/9/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/14/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 7/14/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 7/14/2025 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 7/14/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 7/16/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/16/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/21/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 10/27/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Final | 10/28/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 10/31/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 11/3/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Final | 11/3/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 11/5/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 11/5/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 11/5/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Footing/Foundation/Slab | 11/5/2025 | Approved | WAYNE REGESTER |
| Green Building Final | 11/5/2025 | Approved | WAYNE REGESTER |
| HVAC-Final | 11/5/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 11/5/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Approved | WAYNE REGESTER |
| Service/Power Release | 11/5/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 11/5/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 11/7/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 11/7/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 11/7/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 11/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Pre-Inspection | 11/19/2025 | Approved | WAYNE REGESTER |
| Final | 11/21/2025 | OK to Issue CofO | WAYNE REGESTER |
| PLUMBING-Final | 11/21/2025 | Approved | WAYNE REGESTER |
| Special/Order Compliance | 3/14/2026 | Corrections Issued | RAUL OLAGI |