17601 W HAMLIN ST 91406
Certificate Information: 17601 W HAMLIN ST 91406
- Application / Permit
- 24014-20000-05051
- Plan Check / Job No.
- B24VN22811
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION TO REAR OF (E) SFD WITH INTERIOR REMODEL
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2024 | SERGIO MUNIZ |
| Corrections Issued | 11/19/2024 | SERGIO MUNIZ |
| Plan Check Approved | 12/29/2024 | OMAR GARNICA |
| Issued | 1/13/2025 | APPLICANT |
| CofO in Progress | 1/2/2026 | MORRIS JACKSON |
| Permit Finaled | 1/28/2026 | JOHN JANSON |
| CofO Issued | 1/28/2026 | JOHN JANSON |
| Permit Finaled | 1/28/2026 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/20/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/20/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2024 | EDGAR ALCARAZ |
| Hold | Cleared | 12/19/2024 | SANDRA SOH |
Contact Information
| Contractor | Settle Construction; Lic. No.: 995560-B | 2615 BOTTLE TREE DRIVE PALMDALE, CA 93550 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/20/2025 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 2/20/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 2/20/2025 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Corrections Issued | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 3/17/2025 | Conditional Approval | JON MCHUGH |
| ELECTRICAL-Rough | 3/18/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2025 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 3/18/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Structural Steel Frame | 3/18/2025 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 3/21/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 3/21/2025 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 3/24/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 3/24/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 3/25/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Insulation | 3/25/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Insulation | 3/27/2025 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 4/2/2025 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 4/2/2025 | Approved | MORRIS JACKSON |
| HVAC-Rough | 4/3/2025 | No Access for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/9/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 4/9/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 4/9/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 4/15/2025 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 4/15/2025 | Not Ready for Inspection | JON MCHUGH |
| Deputy Drilled-In Anchors | 4/16/2025 | Partial Approval | SEAN WIRCH |
| Deputy Wood Construction | 4/17/2025 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 4/18/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 4/18/2025 | Approved | JON MCHUGH |
| Green Building Rough | 4/18/2025 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 4/18/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/24/2025 | Corrections Issued | JON MCHUGH |
| Insulation | 4/25/2025 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 4/28/2025 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 5/19/2025 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 6/18/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 6/18/2025 | Corrections Issued | JON MCHUGH |
| Final | 6/18/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 6/18/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 6/18/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 6/18/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 6/27/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 6/27/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 6/27/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Ready | JON MCHUGH |
| Sewer | 6/27/2025 | Corrections Issued | JON MCHUGH |
| Smoke Detectors | 6/27/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 7/11/2025 | No Access for Inspection | JON MCHUGH |
| PLUMBING-Rough | 7/11/2025 | No Access for Inspection | JON MCHUGH |
| Final | 7/21/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 7/21/2025 | No Access for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/21/2025 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 7/21/2025 | No Access for Inspection | JON MCHUGH |
| HVAC-Final | 9/22/2025 | Corrections Issued | JON MCHUGH |
| Sewer | 9/22/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 10/1/2025 | Partial Approval | JON MCHUGH |
| Sewer | 10/6/2025 | Corrections Issued | MORRIS JACKSON |
| Sewer | 10/7/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 10/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 10/24/2025 | Corrections Issued | JON MCHUGH |
| Gas Test | 10/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 10/24/2025 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 10/24/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 10/24/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 10/24/2025 | Not Required | JON MCHUGH |
| Smoke Detectors | 10/24/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 11/6/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 11/6/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Final | 11/6/2025 | Approved | MORRIS JACKSON |
| HVAC-Final | 11/6/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Final | 11/6/2025 | Not Ready for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Not Ready | MORRIS JACKSON |
| Service/Power Release | 11/6/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Smoke Detectors | 11/6/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 11/13/2025 | Not Ready for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 11/13/2025 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 11/13/2025 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 12/10/2025 | Approved | MORRIS JACKSON |
| Final | 12/10/2025 | OK to Issue CofO | MORRIS JACKSON |
| HVAC-Final | 12/10/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 12/10/2025 | Approved | MORRIS JACKSON |
| Service/Power Release | 12/10/2025 | Approved | MORRIS JACKSON |