17601 W HAMLIN ST 91406

Certificate Information: 17601 W HAMLIN ST 91406

Application / Permit
24014-20000-05051
Plan Check / Job No.
B24VN22811
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ADDITION TO REAR OF (E) SFD WITH INTERIOR REMODEL
Permit Issued
Issued on 1/13/2025
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2024 APPLICANT
Assigned to Plan Check Engineer 11/18/2024 SERGIO MUNIZ
Corrections Issued 11/19/2024 SERGIO MUNIZ
Plan Check Approved 12/29/2024 OMAR GARNICA
Issued 1/13/2025 APPLICANT
CofO in Progress 1/2/2026 MORRIS JACKSON
Permit Finaled 1/28/2026 JOHN JANSON
CofO Issued 1/28/2026 JOHN JANSON
Permit Finaled 1/28/2026 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/20/2024 EDGAR ALCARAZ
Sewer availability Cleared 11/20/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 11/21/2024 EDGAR ALCARAZ
Hold Cleared 12/19/2024 SANDRA SOH

Contact Information

Contractor Settle Construction; Lic. No.: 995560-B 2615 BOTTLE TREE DRIVE      PALMDALE, CA 93550
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/20/2025 Approved JON MCHUGH
Footing/Foundation/Slab 2/20/2025 Approved JON MCHUGH
PLUMBING-Rough 2/20/2025 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Corrections Issued MORRIS JACKSON
Deputy Drilled-In Anchors 3/17/2025 Conditional Approval JON MCHUGH
ELECTRICAL-Rough 3/18/2025 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Partial Approval MORRIS JACKSON
PLUMBING-Rough 3/18/2025 Not Ready for Inspection MORRIS JACKSON
Structural Steel Frame 3/18/2025 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 3/21/2025 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 3/21/2025 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 3/24/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Corrections Issued MORRIS JACKSON
PLUMBING-Rough 3/24/2025 Partial Approval MORRIS JACKSON
Green Building Rough 3/25/2025 Not Ready for Inspection MORRIS JACKSON
Insulation 3/25/2025 Not Ready for Inspection MORRIS JACKSON
Insulation 3/27/2025 Partial Approval MORRIS JACKSON
ELECTRICAL-Rough 4/2/2025 Corrections Issued MORRIS JACKSON
PLUMBING-Rough 4/2/2025 Approved MORRIS JACKSON
HVAC-Rough 4/3/2025 No Access for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 4/9/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 4/9/2025 Corrections Issued JON MCHUGH
HVAC-Rough 4/9/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 4/15/2025 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Corrections Issued JON MCHUGH
HVAC-Rough 4/15/2025 Not Ready for Inspection JON MCHUGH
Deputy Drilled-In Anchors 4/16/2025 Partial Approval SEAN WIRCH
Deputy Wood Construction 4/17/2025 Conditional Approval JON MCHUGH
BUILDING-Rough-Frame 4/18/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 4/18/2025 Approved JON MCHUGH
Green Building Rough 4/18/2025 Not Ready for Inspection JON MCHUGH
HVAC-Rough 4/18/2025 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Approved JON MCHUGH
Interior/Exterior Lathing 4/24/2025 Corrections Issued JON MCHUGH
Insulation 4/25/2025 Partial Approval MORRIS JACKSON
Drywall Nailing 4/28/2025 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 5/19/2025 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 6/18/2025 Approved JON MCHUGH
ELECTRICAL-Final 6/18/2025 Corrections Issued JON MCHUGH
Final 6/18/2025 Corrections Issued JON MCHUGH
Green Building Final 6/18/2025 Not Ready for Inspection JON MCHUGH
Green Building Rough 6/18/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Not Ready JON MCHUGH
Smoke Detectors 6/18/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 6/27/2025 Not Ready for Inspection JON MCHUGH
Final 6/27/2025 Not Ready for Inspection JON MCHUGH
Green Building Final 6/27/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Ready JON MCHUGH
Sewer 6/27/2025 Corrections Issued JON MCHUGH
Smoke Detectors 6/27/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 7/11/2025 No Access for Inspection JON MCHUGH
PLUMBING-Rough 7/11/2025 No Access for Inspection JON MCHUGH
Final 7/21/2025 Corrections Issued JON MCHUGH
Green Building Final 7/21/2025 No Access for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 7/21/2025 SGSOV Not Ready JON MCHUGH
Smoke Detectors 7/21/2025 No Access for Inspection JON MCHUGH
HVAC-Final 9/22/2025 Corrections Issued JON MCHUGH
Sewer 9/22/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 10/1/2025 Partial Approval JON MCHUGH
Sewer 10/6/2025 Corrections Issued MORRIS JACKSON
Sewer 10/7/2025 Approved JON MCHUGH
ELECTRICAL-Final 10/24/2025 Not Ready for Inspection JON MCHUGH
Final 10/24/2025 Corrections Issued JON MCHUGH
Gas Test 10/24/2025 Not Ready for Inspection JON MCHUGH
Green Building Final 10/24/2025 Not Ready for Inspection JON MCHUGH
HVAC-Final 10/24/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 10/24/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Not Ready JON MCHUGH
Service/Power Release 10/24/2025 Not Required JON MCHUGH
Smoke Detectors 10/24/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 11/6/2025 Not Ready for Inspection MORRIS JACKSON
Final 11/6/2025 Not Ready for Inspection MORRIS JACKSON
Green Building Final 11/6/2025 Approved MORRIS JACKSON
HVAC-Final 11/6/2025 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Final 11/6/2025 Not Ready for Inspection MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Not Ready MORRIS JACKSON
Service/Power Release 11/6/2025 Not Ready for Inspection MORRIS JACKSON
Smoke Detectors 11/6/2025 Not Ready for Inspection MORRIS JACKSON
Final 11/13/2025 Not Ready for Inspection MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 11/13/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 12/10/2025 Approved MORRIS JACKSON
Final 12/10/2025 OK to Issue CofO MORRIS JACKSON
HVAC-Final 12/10/2025 Approved MORRIS JACKSON
PLUMBING-Final 12/10/2025 Approved MORRIS JACKSON
Service/Power Release 12/10/2025 Approved MORRIS JACKSON