11560 N YARMOUTH AVE 91344
Certificate Information: 11560 N YARMOUTH AVE 91344
- Application / Permit
- 24014-20000-05047
- Plan Check / Job No.
- B24VN22758
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodeling of the existing single family residence and attached garage and patio cover.
- Permit Issued
- Issued on 3/27/2025
- Issuing Office
- Current Status
- Issued on 3/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2024 | JOSEPH RAFOLS |
| Corrections Issued | 11/15/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 12/26/2024 | JOSEPH RAFOLS |
| Issued | 3/27/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/20/2024 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 11/20/2024 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 11/20/2024 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 11/20/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/20/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 12/3/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 12/26/2024 | JOSEPH RAFOLS |
| BHO/Hillside ordinance | Cleared | 3/26/2025 | RYAN CASTRO |
Contact Information
| Contractor | Nextgen Construction Inc The; Lic. No.: 1092708-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/25/2025 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Corrections Issued | STEVEN BACK |
| Special/Order Compliance | 5/5/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 5/13/2025 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 6/20/2025 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 6/26/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 7/3/2025 | Corrections Issued | STEVEN BACK |
| Wood Frame | 7/3/2025 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 7/9/2025 | Approved | STEVEN BACK |
| Insulation | 7/9/2025 | Partial Approval | STEVEN BACK |
| Wood Frame | 7/9/2025 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | No Access for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 12/10/2025 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 1/9/2026 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 1/9/2026 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 1/9/2026 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 1/9/2026 | Corrections Issued | STEVEN BACK |
| Special/Order Compliance | 1/9/2026 | Partial Inspection | HENRY KIM |
| HVAC-Rough | 1/22/2026 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 1/22/2026 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 2/3/2026 | Partial Approval | JEFFREY PARD |
| HVAC-Rough | 2/3/2026 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/6/2026 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 2/6/2026 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/11/2026 | Partial Approval | JEFFREY PARD |
| Deputy Wood Construction | 2/11/2026 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/11/2026 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 3/10/2026 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 3/18/2026 | Conditional Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 3/20/2026 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Approved | STEVEN BACK |
| Insulation | 3/25/2026 | Approved | STEVEN BACK |
| Drywall Nailing | 4/17/2026 | Approved | STEVEN BACK |