9178-9180 N CAYUGA AVE 91352
Certificate Information: 9178-9180 N CAYUGA AVE 91352
- Application / Permit
- 24014-20000-05043
- Plan Check / Job No.
- B24VN22733
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New addition (338 SQ. FT.) to (E) single-family dwelling, located at the residence's rear.
- Permit Issued
- Issued on 11/30/2024
- Issuing Office
- Current Status
- CofO Issued on 10/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2024 | JOHN MESIAS |
| Corrections Issued | 11/16/2024 | JOHN MESIAS |
| Applicant returned to address corrections | 11/20/2024 | MINA HABILI |
| Plan Check Approved | 11/27/2024 | JOHN MESIAS |
| Issued | 11/30/2024 | APPLICANT |
| CofO in Progress | 6/5/2025 | NICHOLAS TROWBRIDGE |
| No Progress | 6/5/2025 | RAUL OLAGI |
| CofO in Progress | 6/5/2025 | RAUL OLAGI |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
| CofO Issued | 10/28/2025 | RUBEN SALAS |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 11/18/2024 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| Hold | Cleared | 1/22/2025 | SANDRA SOH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 1/24/2025 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/28/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 1/28/2025 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/12/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 2/12/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 2/12/2025 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/18/2025 | No Access for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | No Access for Inspection | MATTHEW NELSON |
| HVAC-Rough | 2/18/2025 | No Access for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 2/18/2025 | No Access for Inspection | MATTHEW NELSON |
| Wood Frame | 2/18/2025 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/20/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 2/20/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 2/20/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 2/20/2025 | Partial Approval | JACK KARGODORIAN |
| Insulation | 2/25/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/25/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/27/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/27/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 4/29/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 4/29/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/6/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Final | 5/20/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 6/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |