7906-7908 N LAURELGROVE AVE 91605

Certificate Information: 7906-7908 N LAURELGROVE AVE 91605

Application / Permit
24014-20000-05031
Plan Check / Job No.
B24VN22672
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
MAJOR REMODEL TO (E) S.F.D. TO KEEP 9'-4" (E) WALL WITH ADDITIONS TO CREATE A (N) 2-STORY 30'-0" x 26'-0" SFD WITH ATTACHED 2-STORY 30'-0" x 26'-0" 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT WITH 20'-5" x 20'-10" ATTACHED RECREATION ROOM PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 1/21/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 ALFRED RAMIREZ
Corrections Issued 12/4/2024 ALFRED RAMIREZ
Quality Review Completed 12/11/2024 STEVEN KIM
Building Plans Picked Up 12/12/2024 APPLICANT
Applicant returned to address corrections 12/19/2024 ALFRED RAMIREZ
Applicant returned to address corrections 1/14/2025 ALFRED RAMIREZ
Plan Check Approved 1/21/2025 ALFRED RAMIREZ
Issued 1/21/2025 APPLICANT
CofO in Progress 11/7/2025 MATTHEW NELSON
Permit Finaled 2/14/2026 MICHAEL PELHAM
CofO Issued 2/14/2026 MICHAEL PELHAM
Permit Finaled 2/14/2026 MICHAEL PELHAM

Permit Application Clearance Information

Senate Bill 9 Cleared 12/12/2024 BRENNEN OBETO
Address approval Cleared 12/24/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/26/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 12/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/26/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/5/2025 Partial Approval MATTHEW NELSON
PLUMBING-Rough 3/25/2025 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 3/27/2025 Approved MATTHEW NELSON
Footing/Foundation/Slab 3/27/2025 Approved MATTHEW NELSON
Pre-Inspection 3/28/2025 Partial Inspection MATTHEW NELSON
Deputy Wood Construction 5/14/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 6/23/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 7/8/2025 Approved MATTHEW NELSON
PLUMBING-Rough 7/8/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/14/2025 Approved MATTHEW NELSON
Shower Pan 7/14/2025 Approved MATTHEW NELSON
HVAC-Rough 7/25/2025 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 8/14/2025 Conditional Approval DAVID MATSON
Green Building Rough 8/14/2025 Approved DAVID MATSON
HVAC-Rough 8/14/2025 Corrections Issued DAVID MATSON
HVAC-Rough 8/18/2025 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 8/25/2025 Approved MATTHEW NELSON
HVAC-Rough 8/25/2025 Not Ready for Inspection MATTHEW NELSON
Insulation 8/28/2025 Approved MATTHEW NELSON
Drywall Nailing 9/2/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 10/6/2025 Not Ready for Inspection MATTHEW NELSON
Gas Test 10/6/2025 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 10/6/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 10/6/2025 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 10/15/2025 Approved MATTHEW NELSON
Gas Test 10/15/2025 Approved MATTHEW NELSON
HVAC-Final 10/15/2025 Approved MATTHEW NELSON
PLUMBING-Final 10/15/2025 Approved MATTHEW NELSON
Final 11/3/2025 Partial Approval MATTHEW NELSON
Green Building Final 11/3/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Approved MATTHEW NELSON
Service/Power Release 11/3/2025 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 11/3/2025 Approved MATTHEW NELSON
Final 11/6/2025 OK to Issue CofO MATTHEW NELSON
Service/Power Release 11/6/2025 Approved MATTHEW NELSON