6221 N BAKMAN AVE 91606

Certificate Information: 6221 N BAKMAN AVE 91606

Application / Permit
24014-20000-05020
Plan Check / Job No.
B24VN22632
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT EXISTING DETACHED RECREATION ROOM TO NEW ADU WITH NEW 2 STORY ADDITION PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 1/31/2025
Issuing Office
Current Status
Issued on 1/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/11/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 KHUONG TRUONG
Corrections Issued 11/19/2024 KHUONG TRUONG
Quality Review Completed 11/25/2024 GARO TELMI
Plan Check Approved 1/16/2025 KHUONG TRUONG
Issued 1/31/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 11/27/2024 EDGAR PASCUA
Address approval Cleared 12/31/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/31/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/2/2025 CARLOS AGUILERA
Sewer availability Cleared 1/2/2025 CARLOS AGUILERA
Tenant Habitability Plan Cleared 1/9/2025 RICARDO BOHORQUEZ

Contact Information

Contractor Best Solar 4 Less Inc; Lic. No.: 1018718-B       ,
Contractor Eco Home Builders; Lic. No.: 1018718-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/25/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 3/7/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/7/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 3/14/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 3/14/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 3/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 4/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/29/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/7/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/7/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/13/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/13/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Pre-Inspection 9/3/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/10/2025 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 9/11/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 9/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 9/23/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/23/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/21/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 10/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 11/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 11/12/2025 Approved JOSE AVILA
Shower Pan 11/12/2025 Approved JOSE AVILA
Interior/Exterior Lathing 11/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 11/26/2025 Approved LOUIS ESCOTO
Service/Power Release 1/28/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Inspection 3/23/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/22/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 5/13/2026 Approved GAREN HAYRAPETYAN
Final 5/13/2026 Corrections Issued GAREN HAYRAPETYAN
Gas Test 5/13/2026 Approved GAREN HAYRAPETYAN
Green Building Final 5/13/2026 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 5/13/2026 Approved GAREN HAYRAPETYAN