6667 N ROYER AVE 91307

Certificate Information: 6667 N ROYER AVE 91307

Application / Permit
24014-20000-05003
Plan Check / Job No.
B24VN22534
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR KTCHEN REMODEL,NEW FRONT PORCH AND NEW PATIO, SMOOTH STUCCO REFINISH, REPLACE ALL WINDOWS WITH ENERGY EFFICIENT WINDOWS
Permit Issued
Issued on 12/30/2024
Issuing Office
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 JOE VO
Corrections Issued 11/30/2024 JOE VO
Quality Review Completed 12/3/2024 GARO TELMI
Plan Check Approved 12/23/2024 JOE VO
Issued 12/30/2024 APPLICANT
CofO in Progress 7/23/2025 TROY SANDERS
Permit Finaled 1/27/2026 JOHN JANSON
CofO Issued 1/27/2026 JOHN JANSON
Permit Finaled 1/27/2026 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/3/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/4/2024 EDGAR ALCARAZ

Contact Information

Contractor Miravalle General Contractor Inc; Lic. No.: 1018182-B       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2025 Corrections Issued GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 1/28/2025 Partial Approval GEVORK IPCHYAN
Footing/Foundation/Slab 2/10/2025 Approved GEVORK IPCHYAN
Deputy Wood Construction 2/24/2025 Conditional Approval GEVORK IPCHYAN
ELECTRICAL-Rough 2/25/2025 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 2/25/2025 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 2/25/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 2/25/2025 Approved GEVORK IPCHYAN
Sewer 2/25/2025 Approved GEVORK IPCHYAN
Underground Mechanical 2/25/2025 Approved GEVORK IPCHYAN
Green Building Rough 3/10/2025 Approved TROY SANDERS
Insulation 3/10/2025 Approved TROY SANDERS
Shower Pan 3/10/2025 Approved TROY SANDERS
Drywall Nailing 3/17/2025 Approved TROY SANDERS
BUILDING-Rough-Frame 7/22/2025 Approved TROY SANDERS
ELECTRICAL-Final 7/22/2025 Approved TROY SANDERS
Final 7/22/2025 OK to Issue CofO TROY SANDERS
Green Building Final 7/22/2025 Approved TROY SANDERS
HVAC-Final 7/22/2025 Approved TROY SANDERS
PLUMBING-Final 7/22/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved TROY SANDERS
Smoke Detectors 7/22/2025 Approved TROY SANDERS