12520 W GILMORE AVE 90066

Certificate Information: 12520 W GILMORE AVE 90066

Application / Permit
24014-20000-05002
Plan Check / Job No.
B24VN22529
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, 30'-0" X 28'-6" ADDITION TO (E) SFD PER WFPP. FIRE SPRINKLER (NFPA 13-D) REQUIRED THROUGHOUT.
Permit Issued
Issued on 2/20/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2024 APPLICANT
Assigned to Plan Check Engineer 11/18/2024 ARTIN ZARUKIAN
Corrections Issued 11/19/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/22/2024 APPLICANT
Plan Check Approved 2/12/2025 ARAMIK SHAHMIRZAIAN
Issued 2/20/2025 APPLICANT
CofO in Progress 12/26/2025 ANTHONY EGSON
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/21/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/25/2024 CARLOS RAMIREZ
Sewer availability Cleared 11/25/2024 CARLOS RAMIREZ

Contact Information

Contractor Remma Construction Inc; Lic. No.: 1118967-B 541 S SPRING ST UNIT 310      LOS ANGELES, CA 90013

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2025 Corrections Issued MICHAEL ALLEN
Footing/Foundation/Slab 2/26/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval MICHAEL ALLEN
Special/Order Compliance 3/6/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 4/7/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 4/7/2025 Not Ready for Inspection RUBEN RIVAS
Green Building Rough 4/7/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 4/7/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 4/7/2025 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 4/10/2025 Approved RUBEN RIVAS
Gas Test 4/10/2025 Approved RUBEN RIVAS
HVAC-Rough 4/10/2025 Approved RUBEN RIVAS
PLUMBING-Rough 4/10/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 4/14/2025 Not Ready for Inspection RUBEN RIVAS
Green Building Rough 4/14/2025 Not Ready for Inspection RUBEN RIVAS
Interior/Exterior Lathing 4/14/2025 Partial Approval RUBEN RIVAS
Insulation 4/16/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 4/16/2025 Approved RUBEN RIVAS
Drywall Nailing 4/21/2025 Approved RUBEN RIVAS
Green Building Rough 4/21/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 5/9/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Final 5/23/2025 Approved RUBEN RIVAS
Service/Power Release 5/28/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 6/25/2025 Partial Approval RUBEN RIVAS
Final 6/25/2025 Corrections Issued RUBEN RIVAS
Green Building Final 6/25/2025 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved RUBEN RIVAS
Smoke Detectors 6/25/2025 Approved RUBEN RIVAS
Pre-Inspection 9/29/2025 Corrections Issued RUBEN RIVAS
HVAC-Final 10/14/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Final 10/14/2025 Approved RUBEN RIVAS
HVAC-Final 10/21/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 11/4/2025 Approved DAVID FEILER
Final 11/4/2025 Conditional Approval DAVID FEILER
Final 12/24/2025 OK to Issue CofO ANTHONY EGSON