5411-5413 N RHEA AVE 91356
Certificate Information: 5411-5413 N RHEA AVE 91356
- Application / Permit
- 24014-20000-05001
- Plan Check / Job No.
- B24VN22519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Proposed addition & major remodel to existing Single Family Dwelling & convert existing attached 2-car garage into ADU per CA Govt. Code 65852.2(e)(1)(A) NFPA13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 2/12/2025
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | JAD BASMA |
| Corrections Issued | 11/30/2024 | JAD BASMA |
| Quality Review Completed | 12/3/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 2/5/2025 | JAD BASMA |
| Plan Check Approved | 2/11/2025 | JAD BASMA |
| Issued | 2/12/2025 | APPLICANT |
| CofO in Progress | 1/26/2026 | JOHN KIDWELL |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
| CofO Issued | 2/20/2026 | JOHN JANSON |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/11/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/23/2025 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 1/29/2025 | JERRY KAO |
| GPI Written Notices | Cleared | 1/31/2025 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 1/31/2025 | JAD BASMA |
Contact Information
| Contractor | Chc Building Inc; Lic. No.: 1104747-B | , |
| Engineer | Kim,, Hong Kook; Lic. No.: NA64529 | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/7/2025 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 3/7/2025 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/19/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 4/8/2025 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/7/2025 | Partial Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Partial Inspection | JOHN KIDWELL |
| Green Building Rough | 5/7/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 5/14/2025 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/16/2025 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 5/16/2025 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 5/30/2025 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 6/2/2025 | Approved | JOHN COLEMAN |
| Pre-Inspection | 6/2/2025 | Approved | JOHN COLEMAN |
| ELECTRICAL-Rough | 6/17/2025 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 6/17/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 6/17/2025 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/30/2025 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/30/2025 | Partial Approval | MORRIS JACKSON |
| Insulation | 7/3/2025 | Corrections Issued | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/21/2025 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 7/21/2025 | Approved | JON MCHUGH |
| Shower Pan | 7/21/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 7/21/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 7/29/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/29/2025 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 11/12/2025 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Final | 11/12/2025 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 11/12/2025 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 11/14/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 11/14/2025 | Conditional Approval | JOHN KIDWELL |
| Service/Power Release | 11/14/2025 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/1/2025 | Approved | JOHN KIDWELL |
| Final | 12/1/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 12/1/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 12/1/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 12/1/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 12/9/2025 | Conditional Approval | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 12/9/2025 | Approved | JOHN KIDWELL |
| Smoke Detectors | 12/9/2025 | Approved | JOHN KIDWELL |
| Final | 12/24/2025 | OK to Issue CofO | JOHN KIDWELL |