12612 W HART ST 91605

Certificate Information: 12612 W HART ST 91605

Application / Permit
24014-20000-04977
Plan Check / Job No.
B24VN22375
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 192 SF ADDITIONS TO EXPAND EX KITCHEN & LAUNDRY RM. PROPOSED 269 SF DINING RM ADDITION. CONVERT EX FAMILY RM INTO BEDRM, BATHRM AND CLOSET.
Permit Issued
Issued on 12/12/2024
Issuing Office
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2024 APPLICANT
Assigned to Plan Check Engineer 11/15/2024 HAYATO TSUCHIYA
Corrections Issued 11/16/2024 HAYATO TSUCHIYA
Building Plans Picked Up 11/20/2024 APPLICANT
Plan Check Approved 12/12/2024 YAQUB MIRZA
Issued 12/12/2024 APPLICANT
CofO in Progress 9/12/2025 OGANES TARAKHCHYAN
CofO Issued 10/16/2025 RUBEN SALAS
Permit Finaled 10/16/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/19/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 11/19/2024 RYAN CASTRO
Sewer availability Cleared 11/19/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/23/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 1/24/2025 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/24/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/7/2025 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 2/7/2025 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/14/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 3/14/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 3/14/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 3/18/2025 Approved OGANES TARAKHCHYAN
Insulation 3/21/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 3/25/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 3/25/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/25/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/5/2025 Approved OGANES TARAKHCHYAN
Final 9/5/2025 OK to Issue CofO OGANES TARAKHCHYAN
Gas Test 9/5/2025 Approved OGANES TARAKHCHYAN
Green Building Final 9/5/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 9/5/2025 Approved OGANES TARAKHCHYAN