17701-17703 W LANARK ST 91335

Certificate Information: 17701-17703 W LANARK ST 91335

Application / Permit
24014-20000-04960
Plan Check / Job No.
B24VN22199
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 1ST FLOOR RECREATION ROOM TO (N) ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33(c) and (e)], ADD (N) 2ND FLOOR SB 9 [per SB9 Two-Unit Development Ca Govt Code 65852.21] AND CONNECT TO (E) DETACHED 2 CAR-CARPORT_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 3/11/2025
Issuing Office
Valley
Current Status
CofO Corrected on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 DAWN MC NULTY
Corrections Issued 12/2/2024 DAWN MC NULTY
Quality Review Completed 12/10/2024 OMID HEDAYAT
Building Plans Picked Up 12/17/2024 APPLICANT
Applicant returned to address corrections 12/30/2024 DAWN MC NULTY
Plan Check Approved 3/4/2025 DAWN MC NULTY
Issued 3/11/2025 APPLICANT
CofO in Progress 10/30/2025 ARUTYUN MADATYAN
CofO Issued-Status Void 11/18/2025 JOHN JANSON
Permit Finaled-Status Void 11/18/2025 JOHN JANSON
Re-Activate Permit 11/19/2025 JOHN JANSON
Permit Finaled 11/19/2025 JOHN JANSON
CofO Corrected 11/19/2025 JOHN JANSON
Permit Finaled 11/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/17/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/19/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/19/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/19/2025 BIAINA HARITUNIAN
Senate Bill 9 Cleared 1/21/2025 ASHLEY RODARTE
Construction near power lines Cleared 2/13/2025 ENRIQUE ACOSTA

Contact Information

Architect Samson,, Charles Andrew H; Lic. No.: C22979 6119 MARY ELLEN AVENUE      VAN NUYS, CA 91401
Contractor Suchite J C Construction; Lic. No.: 1020926-B 22308 LANARK STREET      CANOGA PARK, CA 91304
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/17/2025 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 4/24/2025 Approved ARUTYUN MADATYAN
Deputy Steel/Welding 5/5/2025 Conditional Approval ROBERT GOLD
Reinforced Masonry Frame 5/5/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/6/2025 Approved ARUTYUN MADATYAN
Wood Frame 5/15/2025 Corrections Issued JUAN ALVARADO
Deputy Wood Construction 5/16/2025 Partial Approval JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Partial Approval ARUTYUN MADATYAN
Deputy Wood Construction 5/30/2025 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 6/5/2025 Conditional Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 6/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 6/16/2025 Approved ARUTYUN MADATYAN
Green Building Rough 6/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 6/16/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 6/16/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 6/27/2025 Approved JUAN ALVARADO
Underground Mechanical 6/27/2025 Approved JUAN ALVARADO
Wood Frame 7/1/2025 Approved JUAN ALVARADO
Insulation 7/7/2025 Approved TROY SANDERS
Interior/Exterior Lathing 7/7/2025 Partial Approval TROY SANDERS
Drywall Nailing 7/11/2025 Approved ARUTYUN MADATYAN
Green Building Rough 7/11/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 7/11/2025 Approved ARUTYUN MADATYAN
Special/Order Compliance 8/7/2025 Partial Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 9/10/2025 Approved ARUTYUN MADATYAN
Final 9/10/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 9/10/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 9/10/2025 Approved ARUTYUN MADATYAN
Final 9/25/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 9/25/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 10/7/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 10/7/2025 Approved ARUTYUN MADATYAN
Service/Power Release 10/7/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 10/30/2025 Approved ARUTYUN MADATYAN
Final 10/30/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 10/30/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 10/30/2025 Approved ARUTYUN MADATYAN