13132 W WELBY WAY 91606
Certificate Information: 13132 W WELBY WAY 91606
- Application / Permit
- 24014-20000-04931
- Plan Check / Job No.
- B24VN21941
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 28'-2" X13'5" BEDRM W/ BATH & CLOSET & FAMILY RM ADDITION. CONVERT EX FAMILY RM INTO KITCHEN. DEMO CLOSET TO ENLARGE EX BEDRM. DEMO WALL BETWEEN EX KITCHEN & LIVINGRM & CONVERT EX KITCHEN INTO DINING RM. NEW DOORS AND WINDOWS. PER ENGINEER DEISGN.
- Permit Issued
- Issued on 2/6/2025
- Issuing Office
- Current Status
- CofO Issued on 7/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 11/12/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/14/2024 | APPLICANT |
| Applicant returned to address corrections | 11/20/2024 | ALEC MOUSAKHANIAN |
| Issued | 2/6/2025 | APPLICANT |
| CofO in Progress | 7/8/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| CofO Issued | 7/10/2025 | RUBEN SALAS |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/11/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 3/10/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/17/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/17/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/25/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/25/2025 | Partial Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/1/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/16/2025 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/16/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/16/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/16/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/17/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 4/17/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/2/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 7/2/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/2/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 7/2/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/2/2025 | Approved | OGANES TARAKHCHYAN |