5806 N BEN AVE 91607

Certificate Information: 5806 N BEN AVE 91607

Application / Permit
24014-20000-04928
Plan Check / Job No.
B24VN21925
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH ADDITIONS INTO A (N) 2-STORY IRREGULARSHAPED 22'-0" x 32'-7" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER ENGINEERING
Permit Issued
Issued on 2/19/2025
Issuing Office
Valley
Current Status
Issued on 2/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/4/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 ALFRED RAMIREZ
Corrections Issued 11/18/2024 ALFRED RAMIREZ
Quality Review Completed 11/19/2024 STEVEN KIM
Building Plans Picked Up 11/21/2024 APPLICANT
Applicant returned to address corrections 12/11/2024 ALFRED RAMIREZ
Plan Check Approved 2/19/2025 ALFRED RAMIREZ
Issued 2/19/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/21/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 11/21/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/26/2024 RYAN CASTRO
Sewer availability Cleared 11/26/2024 RYAN CASTRO
Construction near power lines Cleared 2/7/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2025 Corrections Issued JOSE AVILA
Underground Mechanical 3/4/2025 Partial Approval JOSE AVILA
Footing/Foundation/Slab 3/11/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/13/2025 Partial Approval JOSE AVILA
Footing/Foundation/Slab 3/26/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/28/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Corrections Issued JOSE AVILA
HVAC-Rough 6/24/2025 Approved JOSE AVILA
PLUMBING-Rough 6/24/2025 Approved JOSE AVILA
ELECTRICAL-Rough 7/1/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Approved JOSE AVILA
Shower Pan 7/1/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 7/10/2025 Approved JOSE AVILA
Green Building Rough 7/10/2025 Approved JOSE AVILA
MERV13>=Rough 7/10/2025 Approved JOSE AVILA
Insulation 7/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 7/15/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 7/29/2025 Approved JOSE AVILA
Insulation 7/29/2025 Approved JOSE AVILA
Interior/Exterior Lathing 7/29/2025 Approved JOSE AVILA
ELECTRICAL-Final 10/30/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 10/30/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 10/31/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 10/31/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 1/23/2026 Approved JOSE AVILA
HVAC-Final 1/23/2026 Approved JOSE AVILA
Service/Power Release 1/23/2026 Approved JOSE AVILA