6622-6624 N MELBA AVE 91307
Certificate Information: 6622-6624 N MELBA AVE 91307
- Application / Permit
- 24014-20000-04915
- Plan Check / Job No.
- B24VN21864
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE (21'-1" X 21') AND ADDITION OF ( 16'-3"X3') TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(C) AND (e). ADDITION OF IRREGULAR SHAPE (21' X 34' - 7") TO SFD AND ADDITION OF IRREGULAR SHAPE (23' X 20' -1") 2 CAR GARAGE. NFPA13D FIRE SPRINKLERS THOUGHOUT
- Permit Issued
- Issued on 12/13/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2024 | EDWARD MEHRABIAN |
| Corrections Issued | 11/18/2024 | EDWARD MEHRABIAN |
| Quality Review Completed | 11/22/2024 | OMID HEDAYAT |
| Plan Check Approved | 12/12/2024 | EDWARD MEHRABIAN |
| Issued | 12/13/2024 | APPLICANT |
| CofO in Progress | 11/14/2025 | GEVORK IPCHYAN |
| Permit Finaled | 12/30/2025 | JOHN JANSON |
| CofO Issued | 12/30/2025 | JOHN JANSON |
| Permit Finaled | 12/30/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/16/2025 | Partial Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 1/28/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 1/28/2025 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 1/31/2025 | Partial Approval | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/21/2025 | Corrections Issued | SCOTT SOBEL |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 4/9/2025 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 4/9/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 4/9/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/9/2025 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/9/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 4/23/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 5/2/2025 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 5/7/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 5/7/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/7/2025 | Approved | GEVORK IPCHYAN |
| Final | 10/29/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 10/29/2025 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 10/29/2025 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Final | 11/13/2025 | Approved | GEVORK IPCHYAN |
| Final | 11/13/2025 | OK to Issue CofO | GEVORK IPCHYAN |
| HVAC-Final | 11/13/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 11/13/2025 | Approved | GEVORK IPCHYAN |
| Service/Power Release | 11/13/2025 | Approved | GEVORK IPCHYAN |
| Smoke Detectors | 11/13/2025 | Approved | GEVORK IPCHYAN |