6120 N LAURELGROVE AVE 91606
Certificate Information: 6120 N LAURELGROVE AVE 91606
- Application / Permit
- 24014-20000-04898
- Plan Check / Job No.
- B24VN21811
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & ADDITION TO (E) SINGLE FAMILY DWELLING (NEW DIM: 58'-6" x 67'-9" IRR. SHAPED ONE-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE & PATIO COVER; ALL NEW ROOF); NFPA-13D THRU-OUT
- Permit Issued
- Issued on 1/2/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | SEAN SHAHMIRI |
| Corrections Issued | 11/13/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 11/13/2024 | STEVEN KIM |
| Building Plans Picked Up | 11/15/2024 | APPLICANT |
| Applicant returned to address corrections | 12/17/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 12/30/2024 | SEAN SHAHMIRI |
| Issued | 1/2/2025 | APPLICANT |
| CofO in Progress | 6/4/2026 | WAYNE REGESTER |
| CofO Issued | 7/1/2026 | RUBEN SALAS |
| Permit Finaled | 7/1/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 11/20/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/20/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/20/2024 | BIAINA HARITUNIAN |
| Address approval | Cleared | 12/17/2024 | FADI ABBOUD |
Contact Information
| Contractor | A M Acoustics Inc; Lic. No.: 756269-B | 5215 AVENIDA ORIENTE TARZANA, CA 91356 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/21/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 1/22/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 1/31/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Underground Mechanical | 4/17/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 5/2/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| MERV13>=Rough | 5/2/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 5/6/2025 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 5/12/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/12/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/20/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/21/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 5/23/2025 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 5/23/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/4/2025 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 6/11/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 6/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 6/20/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 7/8/2025 | Partial Approval | LOUIS ESCOTO |
| ELECTRICAL-Rough | 8/20/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/20/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 8/20/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/10/2025 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 2/20/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 2/27/2026 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 3/4/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 3/4/2026 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Final | 3/4/2026 | Approved | WAYNE REGESTER |
| Service/Power Release | 3/4/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 5/6/2026 | Approved | WAYNE REGESTER |
| Drywall Nailing | 5/20/2026 | Approved | WAYNE REGESTER |
| Final | 5/20/2026 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 5/20/2026 | Approved | WAYNE REGESTER |
| Green Building Final | 5/20/2026 | Approved | WAYNE REGESTER |
| MERV13>=Final | 5/20/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 5/20/2026 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 5/20/2026 | Approved | WAYNE REGESTER |
| Final | 6/3/2026 | OK to Issue CofO | WAYNE REGESTER |