15048 W MARLIN PL 91405
Certificate Information: 15048 W MARLIN PL 91405
- Application / Permit
- 24014-20000-04890
- Plan Check / Job No.
- B24VN21726
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 17'6" X 20' ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING TO ADD A NEW BEDROOM AND BATHROOM. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- CofO in Progress on 1/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | MADISON ODELL |
| Corrections Issued | 11/8/2024 | MADISON ODELL |
| Applicant returned to address corrections | 11/22/2024 | NGHI SU |
| Plan Check Approved | 11/25/2024 | MADISON O'DELL |
| Issued | 12/5/2024 | APPLICANT |
| CofO in Progress | 1/16/2026 | VINCENT HANLEY |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George H; Lic. No.: NA64144 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/24/2024 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/6/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/6/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/19/2025 | Conditional Approval | RYAN SALAZAR |
| PLUMBING-Rough | 2/19/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | RYAN SALAZAR |
| Service/Power Release | 2/26/2025 | Approved | RYAN SALAZAR |
| Insulation | 3/4/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/13/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/13/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 3/13/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/15/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/15/2026 | Approved | VINCENT HANLEY |
| Final | 1/15/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 1/15/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/15/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 1/15/2026 | Approved | VINCENT HANLEY |