17217 W KINGSBURY ST 91344

Certificate Information: 17217 W KINGSBURY ST 91344

Application / Permit
24014-20000-04887
Plan Check / Job No.
B24VN21687
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
9'-0" X 11'-6" ADDITION TO THE EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 11/8/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 DANIEL ABRAMYAN
Corrections Issued 10/31/2024 DANIEL ABRAMYAN
Issued 11/8/2024 APPLICANT
CofO in Progress 4/24/2025 RAUL OLAGI
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/5/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/8/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/21/2024 Conditional Approval ROBERT GOLD
Sewer 11/22/2024 Approved JAVIER RAMOS JR
Special/Order Compliance 11/22/2024 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 11/22/2024 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 12/10/2024 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/31/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 12/31/2024 Approved JAVIER RAMOS JR
HVAC-Rough 12/31/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/31/2024 Partial Approval JAVIER RAMOS JR
Special/Order Compliance 12/31/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/7/2025 Partial Approval JAVIER RAMOS JR
Insulation 1/7/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/7/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/6/2025 Approved JAVIER RAMOS JR
Drywall Nailing 2/6/2025 Approved JAVIER RAMOS JR
Green Building Rough 2/6/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 2/6/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 2/6/2025 Approved JAVIER RAMOS JR
Shower Pan 2/6/2025 Approved JAVIER RAMOS JR
Final 3/25/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/25/2025 Approved CHRISTOPHER ROJAS
Green Building Final 3/25/2025 Approved CHRISTOPHER ROJAS
Smoke Detectors 3/25/2025 Approved CHRISTOPHER ROJAS
Final 4/24/2025 OK to Issue CofO RAUL OLAGI