175 E 49TH ST 90011

Certificate Information: 175 E 49TH ST 90011

Application / Permit
24014-20000-04856
Plan Check / Job No.
B24VN21456
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. (E) SFD FIRE DAMAGED REPAIR AND 280 SF ADDITION. PER ENGINEERING DESIGN. NFPA 13D FIRE SPRINKLERS PROVIDED.
Permit Issued
Issued on 2/14/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 ALFREDO JARA
Corrections Issued 11/17/2024 ALFREDO JARA
Applicant returned to address corrections 1/10/2025 ALFREDO JARA
Applicant returned to address corrections 1/21/2025 ALFREDO JARA
Plan Check Approved 2/13/2025 ALFREDO JARA
Issued 2/14/2025 APPLICANT
CofO in Progress 6/2/2026 ALEJANDRO DE ARTOLA
Permit Finaled 6/4/2026 DEROLD HAUFF
CofO Issued 6/4/2026 DEROLD HAUFF
Permit Finaled 6/4/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/28/2025 TREVOR QUAN
Sewer availability Cleared 1/28/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/29/2025 TREVOR QUAN
ZI Cleared 2/10/2025 MATHEW QUAN

Contact Information

Contractor V H Builders And Restoration; Lic. No.: 992117-B       ,
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 5/20/2025 Conditional Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 7/15/2025 Corrections Issued LUIS CASTRO
Excavation/Setback/Form/Re-Bar 7/17/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 8/11/2025 Corrections Issued SABAS ALONSO
Underground Mechanical 8/11/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 11/6/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 11/6/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 11/6/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 11/6/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 11/10/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 11/10/2025 Approved BARRY HACHE
PLUMBING-Rough 11/10/2025 Corrections Issued BARRY HACHE
Deputy Wood Construction 11/13/2025 Conditional Approval ANTHONY RAMOS
ELECTRICAL-Rough 12/3/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 12/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/24/2025 Corrections Issued LUIS CASTRO
Green Building Rough 12/24/2025 Not Ready for Inspection LUIS CASTRO
Interior/Exterior Lathing 12/24/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 12/24/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 12/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/30/2025 Approved RAUL BARAJAS
HVAC-Rough 12/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/30/2025 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/8/2026 Approved ANTHONY RAMOS
HVAC-Rough 1/8/2026 Approved ANTHONY RAMOS
Insulation 1/8/2026 Approved ANTHONY RAMOS
Drywall Nailing 1/15/2026 Approved WILLIAM SIERRA
Final 3/25/2026 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 3/25/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/7/2026 Approved ALEJANDRO DE ARTOLA
Gas Test 5/7/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/7/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/7/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/19/2026 Approved RAUL BARAJAS
Final 5/29/2026 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/29/2026 Approved ALEJANDRO DE ARTOLA
Green Building Final 5/29/2026 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 5/29/2026 Approved ALEJANDRO DE ARTOLA
Final 6/2/2026 OK to Issue CofO ALEJANDRO DE ARTOLA