10880 W TENNESSEE AVE 90064

Certificate Information: 10880 W TENNESSEE AVE 90064

Application / Permit
24014-20000-04854
Plan Check / Job No.
B24VN21448
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH ADDITIONS INTO A (E) DETACHED 2-STORY 20'-0" x 31'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/3/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 ALFRED RAMIREZ
Corrections Issued 11/2/2024 ALFRED RAMIREZ
Quality Review Completed 11/5/2024 STEVEN KIM
Building Plans Picked Up 11/7/2024 APPLICANT
Plan Check Approved 3/3/2025 ALFRED RAMIREZ
Issued 3/3/2025 APPLICANT
CofO in Progress 12/9/2025 JAVIER RAMOS JR
Permit Finaled 12/16/2025 RICHARD STEINBACH
CofO Issued 12/16/2025 RICHARD STEINBACH
Permit Finaled 12/16/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction within easement Cleared 1/8/2025 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/13/2025 DARIN LAM
Sewer availability Cleared 1/13/2025 DARIN LAM
Specific Plan Cleared 2/14/2025 PEDRO AYALA
Address approval Cleared 3/3/2025 TREVOR QUAN
Grading Pre-Inspection Cleared 3/3/2025 ALFRED RAMIREZ
Roof/Waste drainage to street Cleared 3/3/2025 DARIN LAM

Contact Information

Contractor Golden Clubs Construction Inc; Lic. No.: 1068883-B 4339 ALHAMA DRIVE      WOODLAND HILLS, CA 91364
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2025 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 4/29/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/29/2025 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Corrections Issued KIRK SANDERS
Green Building Rough 5/30/2025 Not Ready for Inspection KIRK SANDERS
Wood Frame 5/30/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 6/11/2025 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 6/17/2025 Partial Approval MEL KHACHATOURIAN
Sewer 6/17/2025 Not Ready for Inspection MEL KHACHATOURIAN
Sewer 6/26/2025 Approved ARAM AVEDISIAN
Underground Mechanical 6/26/2025 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 7/1/2025 Corrections Issued MEL KHACHATOURIAN
HVAC-Rough 7/11/2025 Approved ARAM AVEDISIAN
Insulation 7/11/2025 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 7/11/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/21/2025 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 7/21/2025 Approved MEL KHACHATOURIAN
Green Building Rough 7/21/2025 Approved MEL KHACHATOURIAN
Insulation 7/21/2025 Not Ready for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 7/21/2025 Partial Approval MEL KHACHATOURIAN
Wood Frame 7/21/2025 Approved MEL KHACHATOURIAN
Insulation 7/23/2025 Approved EVAN COOPER
Drywall Nailing 8/5/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 8/5/2025 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 8/7/2025 Approved SEAN HAUPT
Service/Power Release 9/24/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 11/21/2025 Corrections Issued KIRK SANDERS
Final 11/21/2025 Corrections Issued KIRK SANDERS
Green Building Final 11/21/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 11/21/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 11/21/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 11/21/2025 Partial Approval KIRK SANDERS
Smoke Detectors 11/24/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 12/5/2025 Approved EVAN COOPER
Final 12/5/2025 Corrections Issued EVAN COOPER
Green Building Final 12/5/2025 Approved EVAN COOPER
HVAC-Final 12/5/2025 Approved EVAN COOPER
PLUMBING-Final 12/5/2025 Approved EVAN COOPER
Service/Power Release 12/5/2025 Approved EVAN COOPER
Smoke Detectors 12/5/2025 Approved EVAN COOPER
Final 12/9/2025 OK to Issue CofO JAVIER RAMOS JR