10880 W TENNESSEE AVE 90064
Certificate Information: 10880 W TENNESSEE AVE 90064
- Application / Permit
- 24014-20000-04854
- Plan Check / Job No.
- B24VN21448
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH ADDITIONS INTO A (E) DETACHED 2-STORY 20'-0" x 31'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/3/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | ALFRED RAMIREZ |
| Corrections Issued | 11/2/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 11/5/2024 | STEVEN KIM |
| Building Plans Picked Up | 11/7/2024 | APPLICANT |
| Plan Check Approved | 3/3/2025 | ALFRED RAMIREZ |
| Issued | 3/3/2025 | APPLICANT |
| CofO in Progress | 12/9/2025 | JAVIER RAMOS JR |
| Permit Finaled | 12/16/2025 | RICHARD STEINBACH |
| CofO Issued | 12/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction within easement | Cleared | 1/8/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2025 | DARIN LAM |
| Sewer availability | Cleared | 1/13/2025 | DARIN LAM |
| Specific Plan | Cleared | 2/14/2025 | PEDRO AYALA |
| Address approval | Cleared | 3/3/2025 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 3/3/2025 | ALFRED RAMIREZ |
| Roof/Waste drainage to street | Cleared | 3/3/2025 | DARIN LAM |
Contact Information
| Contractor | Golden Clubs Construction Inc; Lic. No.: 1068883-B | 4339 ALHAMA DRIVE WOODLAND HILLS, CA 91364 |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2025 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/29/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/29/2025 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 5/30/2025 | Not Ready for Inspection | KIRK SANDERS |
| Wood Frame | 5/30/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 6/11/2025 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Conditional Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/17/2025 | Partial Approval | MEL KHACHATOURIAN |
| Sewer | 6/17/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Sewer | 6/26/2025 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 6/26/2025 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/1/2025 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Rough | 7/11/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 7/11/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/11/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/21/2025 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 7/21/2025 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 7/21/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 7/21/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 7/21/2025 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 7/21/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 7/23/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 8/5/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/5/2025 | Partial Approval | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/7/2025 | Approved | SEAN HAUPT |
| Service/Power Release | 9/24/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/21/2025 | Corrections Issued | KIRK SANDERS |
| Final | 11/21/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 11/21/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 11/21/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 11/21/2025 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 11/21/2025 | Partial Approval | KIRK SANDERS |
| Smoke Detectors | 11/24/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 12/5/2025 | Approved | EVAN COOPER |
| Final | 12/5/2025 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/5/2025 | Approved | EVAN COOPER |
| HVAC-Final | 12/5/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/5/2025 | Approved | EVAN COOPER |
| Service/Power Release | 12/5/2025 | Approved | EVAN COOPER |
| Smoke Detectors | 12/5/2025 | Approved | EVAN COOPER |
| Final | 12/9/2025 | OK to Issue CofO | JAVIER RAMOS JR |