19170-19172 W LIGGETT ST 91324

Certificate Information: 19170-19172 W LIGGETT ST 91324

Application / Permit
24014-20000-04850
Plan Check / Job No.
B24VN21388
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF (E) SFD AND ATTACHED GARAGE WITH ADDTION TO AN ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 12/12/2024
Issuing Office
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2024 APPLICANT
Assigned to Plan Check Engineer 11/4/2024 CARLOS MONTES
Corrections Issued 11/5/2024 CARLOS MONTES
Applicant returned to address corrections 11/27/2024 JOHN MESIAS
Applicant returned to address corrections 12/5/2024 CARLOS MONTES
Plan Check Approved 12/11/2024 CARLOS MONTES
Issued 12/12/2024 APPLICANT
CofO in Progress 6/1/2026 JACK KARGODORIAN
Permit Finaled 6/2/2026 JOHN JANSON
CofO Issued 6/2/2026 JOHN JANSON
Permit Finaled 6/2/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/7/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/7/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/7/2024 CARLOS AGUILERA
Sewer availability Cleared 11/7/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/3/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 2/4/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 2/4/2025 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 4/17/2025 Not Ready for Inspection DAVID SCANTLIN
Drywall Nailing 4/17/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 4/17/2025 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Approved KRISTEN CAUSEY
Green Building Rough 9/25/2025 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Rough 10/15/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/15/2025 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 11/3/2025 Approved DAVID SCANTLIN
ELECTRICAL-Rough 11/3/2025 Approved DAVID SCANTLIN
Green Building Rough 11/3/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 11/3/2025 Approved DAVID SCANTLIN
Insulation 11/17/2025 Approved DAVID SCANTLIN
Shower Pan 11/17/2025 Approved DAVID SCANTLIN
Drywall Nailing 11/24/2025 Approved KRISTEN CAUSEY
Final 3/31/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 3/31/2026 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 3/31/2026 Approved JACK KARGODORIAN
Final 4/21/2026 Corrections Issued HENRY KIM
Green Building Final 4/21/2026 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Approved HENRY KIM
Service/Power Release 4/21/2026 Corrections Issued HENRY KIM
Final 4/28/2026 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 4/28/2026 Approved JACK KARGODORIAN