12821 N DENTON AVE 91342

Certificate Information: 12821 N DENTON AVE 91342

Application / Permit
24014-20000-04829
Plan Check / Job No.
B24VN21285
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* ADD 15' X 1206" TO FIRST FLOOR AND 34' X 20' TO SECOND FLOOR AND CONVERT EXISTING DETACHED GARAGE TO NEW TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/24/2025
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 SELLA BENYAMIN
Corrections Issued 11/21/2024 SELLA BENYAMIN
Quality Review Completed 11/22/2024 STEVEN KIM
Plan Check Approved 1/23/2025 SELLA BENYAMIN
Issued 1/24/2025 APPLICANT
CofO in Progress 7/1/2025 KEVIN BERBERYAN
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/2/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 12/2/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/5/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 1/23/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/28/2025 Partial Approval KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 1/31/2025 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 1/31/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Conditional Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 3/17/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 3/17/2025 Approved KEVIN BERBERYAN
HVAC-Rough 3/17/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 3/17/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 3/21/2025 Partial Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 3/21/2025 Approved KEVIN BERBERYAN
Insulation 3/25/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 3/28/2025 Corrections Issued KEVIN BERBERYAN
Drywall Nailing 3/28/2025 Conditional Approval KEVIN BERBERYAN
Sewer 3/28/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 5/6/2025 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Final 5/6/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 5/6/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Final 5/6/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Final 5/6/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/6/2025 SGSOV No Gas KEVIN BERBERYAN
Service/Power Release 5/6/2025 Not Required KEVIN BERBERYAN
Smoke Detectors 5/6/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 5/23/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 5/23/2025 Approved KEVIN BERBERYAN
Final 5/23/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Final 5/23/2025 Approved KEVIN BERBERYAN
PLUMBING-Final 5/23/2025 Approved KEVIN BERBERYAN
Final 7/1/2025 OK to Issue CofO KEVIN BERBERYAN