2737-2739 S MIDVALE AVE 90064

Certificate Information: 2737-2739 S MIDVALE AVE 90064

Application / Permit
24014-20000-04827
Plan Check / Job No.
B24VN21244
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY IRREGULAR SHAPE ( 49'-2" X 38'-11") ADDITION TO (E) SFD AND CONVERT (15'-8" X 24' ) OF (E) SFD TO JADU PER GCS 66323(a)(1) and 66333. NFPA 13D Fire Sprinklered throughout.
Permit Issued
Issued on 7/23/2025
Issuing Office
Valley
Current Status
Issued on 7/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/29/2024 APPLICANT
Assigned to Plan Check Engineer 11/7/2024 EDWARD MEHRABIAN
Corrections Issued 11/18/2024 EDWARD MEHRABIAN
Quality Review Completed 11/21/2024 OMID HEDAYAT
Building Plans Picked Up 11/22/2024 APPLICANT
Applicant returned to address corrections 7/16/2025 EDWARD MEHRABIAN
Plan Check Approved 7/17/2025 EDWARD MEHRABIAN
Issued 7/23/2025 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 2/4/2025 FREDDY GARCIA
Address approval Cleared 2/6/2025 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 2/18/2025 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 2/18/2025 LIAM ODONOVAN
Sewer availability Cleared 2/18/2025 LIAM ODONOVAN
Hydrant and Access approval Cleared 3/24/2025 KENNETH FRASER
Specific Plan Cleared 4/18/2025 KYLE WINSTON
Flood clearance Cleared 4/21/2025 TUYEN LE
Miscellaneous Cleared 5/5/2025 DIANA RENTERIA
GPI Written Notices Cleared 6/24/2025 EDWARD MEHRABIAN
Grading Pre-Inspection Cleared 6/24/2025 LANNY MERRICK

Contact Information

Contractor Atari Home Builders Inc; Lic. No.: 1088740-B 19730 VENTURA BLVD SUITE E1      WOODLAND HILLS, CA 91364
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/5/2025 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 8/5/2025 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 8/18/2025 Not Ready for Inspection KIRK SANDERS
FLOOD-Elevation Certificate 8/18/2025 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 8/18/2025 Corrections Issued KIRK SANDERS
FLOOD-Elevation Certificate 8/29/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 8/29/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 9/9/2025 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 9/10/2025 Partial Approval EVAN COOPER
FLOOD-Proofing Certificate 9/10/2025 Not Ready for Inspection EVAN COOPER
Green Building Rough 9/10/2025 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 9/10/2025 Not Ready for Inspection EVAN COOPER
Rough-Elec/Plmb/HVAC 9/10/2025 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved MICHAEL ALLEN
HVAC-Final 10/24/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 10/24/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 10/24/2025 Approved KIRK SANDERS
ELECTRICAL-Rough 10/27/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 10/27/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 11/4/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 11/4/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 11/4/2025 Partial Approval KIRK SANDERS
Wood Frame 11/7/2025 Not Ready for Inspection MICHAEL ALLEN
Shower Pan 11/19/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 11/21/2025 Approved KIRK SANDERS
FLOOD-Elevation Certificate 11/21/2025 Approved KIRK SANDERS
FLOOD-Proofing Certificate 11/21/2025 Approved KIRK SANDERS
Green Building Rough 11/21/2025 Approved KIRK SANDERS
MERV13>=Rough 11/21/2025 Approved KIRK SANDERS
Verify Sprinkler Sign Off 11/21/2025 Approved KIRK SANDERS
Wood Frame 11/21/2025 Approved KIRK SANDERS
Insulation 12/2/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 12/2/2025 Corrections Issued KIRK SANDERS
Drywall Nailing 12/10/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 12/10/2025 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 12/22/2025 Approved KIRK SANDERS
Drywall Nailing 5/4/2026 Approved MICHAEL LEWIS
ELECTRICAL-Final 5/4/2026 Approved MICHAEL LEWIS
Final 5/4/2026 Corrections Issued MICHAEL LEWIS
Green Building Final 5/4/2026 Approved MICHAEL LEWIS
HVAC-Final 5/4/2026 Corrections Issued MICHAEL LEWIS
MERV13>=Final 5/4/2026 Approved MICHAEL LEWIS
PLUMBING-Final 5/4/2026 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/4/2026 SGSOV Approved MICHAEL LEWIS
Service/Power Release 5/4/2026 Approved MICHAEL LEWIS
Smoke Detectors 5/4/2026 Approved MICHAEL LEWIS
Final 5/18/2026 Corrections Issued HERBERT GIRON
HVAC-Final 5/18/2026 Approved HERBERT GIRON