13715 W OSBORNE ST 91331
Certificate Information: 13715 W OSBORNE ST 91331
- Application / Permit
- 24014-20000-04825
- Plan Check / Job No.
- B24VN21216
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert and addition to existing garage to new irregular shaped two stories 28' 6" x 22' 11" ADU per LAMC 12.22 A.33(b)(1)3. All work done per engineer.
- Permit Issued
- Issued on 3/13/2025
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | NAREG ATARIAN |
| Corrections Issued | 11/2/2024 | NAREG ATARIAN |
| Quality Review Completed | 11/6/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/19/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 3/5/2025 | NAREG ATARIAN |
| Plan Check Approved | 3/13/2025 | NAREG ATARIAN |
| Issued | 3/13/2025 | APPLICANT |
| CofO in Progress | 8/15/2025 | VINCENT HANLEY |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
| CofO Issued | 8/27/2025 | RUBEN SALAS |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/15/2025 | EDGAR PASCUA |
| Construction within easement | Cleared | 1/15/2025 | EDGAR PASCUA |
| Address approval | Cleared | 2/10/2025 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 2/10/2025 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2025 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 2/14/2025 | CARLOS RAMIREZ |
Contact Information
| Contractor | Mg General Construction Inc; Lic. No.: 1086142-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/25/2025 | Corrections Issued | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 4/11/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/11/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 4/15/2025 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/22/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/22/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/3/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 6/3/2025 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 6/3/2025 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 6/5/2025 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 6/12/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 6/12/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/12/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/12/2025 | Corrections Issued | VINCENT HANLEY |
| Underground Mechanical | 6/12/2025 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/16/2025 | Approved | VINCENT HANLEY |
| Insulation | 6/16/2025 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/16/2025 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 6/16/2025 | Approved | VINCENT HANLEY |
| Insulation | 6/23/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/23/2025 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 6/27/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/27/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/31/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 7/31/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/31/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/31/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 7/31/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/14/2025 | Approved | VINCENT HANLEY |
| Final | 8/14/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 8/14/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/14/2025 | Approved | VINCENT HANLEY |