8343 N JUMILLA AVE 91306

Certificate Information: 8343 N JUMILLA AVE 91306

Application / Permit
24014-20000-04824
Plan Check / Job No.
B24VN21215
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 20' X 21'6" ADDITION TO REAR OF SFD TO ADD ONE NEW BEDROOM AND 2 NEW BATHROOMS.
Permit Issued
Issued on 11/16/2024
Issuing Office
Current Status
CofO in Progress on 5/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/30/2024 APPLICANT
Assigned to Plan Check Engineer 11/5/2024 MADISON ODELL
Corrections Issued 11/6/2024 MADISON ODELL
Plan Check Approved 11/14/2024 MADISON O'DELL
Issued 11/16/2024 APPLICANT
CofO in Progress 5/18/2026 CHRIS CHRISTENSEN
No Progress 5/29/2026 CHRISTOPHER WILSON
CofO in Progress 5/29/2026 CHRISTOPHER WILSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/8/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/8/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/13/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Bui,, Mai Phuong; Lic. No.: C61280 7445 LURLINE AVE      WINNETKA, CA 91306

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/5/2025 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 7/7/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Partial Approval CHRIS CHRISTENSEN
Insulation 1/5/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/5/2026 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 1/8/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/8/2026 Approved CHRIS CHRISTENSEN
Shower Pan 1/8/2026 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/30/2026 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 4/30/2026 Approved CHRIS CHRISTENSEN
Final 4/30/2026 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/30/2026 Approved CHRIS CHRISTENSEN
HVAC-Final 4/30/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Final 4/30/2026 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/30/2026 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 4/30/2026 Approved CHRIS CHRISTENSEN
Final 5/15/2026 OK to Issue CofO CHRIS CHRISTENSEN
Special/Order Compliance 6/11/2026 Corrections Issued CHRIS CHRISTENSEN