10448 N WOODLEY AVE 91344

Certificate Information: 10448 N WOODLEY AVE 91344

Application / Permit
24014-20000-04807
Plan Check / Job No.
B24VN21139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO & CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 11/1/2024 ARTIN ZARUKIAN
Corrections Issued 11/2/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/4/2024 APPLICANT
Applicant returned to address corrections 3/12/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 3/12/2025 SERGIO MUNIZ
Issued 3/12/2025 APPLICANT
CofO in Progress 9/3/2025 CHRISTOPHER ROJAS
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/4/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/4/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/4/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/5/2024 LEE GUILBEAUX
Sewer availability Cleared 11/5/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/23/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 4/23/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/5/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/17/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/17/2025 Approved CHRISTOPHER ROJAS
Gas Test 6/17/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 6/17/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 6/17/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 6/17/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/23/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/23/2025 Approved CHRISTOPHER ROJAS
Insulation 7/3/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 7/3/2025 Partial Approval MICHAEL CORTEZ
Drywall Nailing 7/8/2025 Approved MICHAEL CORTEZ
Shower Pan 7/8/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 8/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/27/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/27/2025 Approved CHRISTOPHER ROJAS
Green Building Final 8/27/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 8/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 8/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 8/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 9/2/2025 Approved CHRISTOPHER ROJAS
Final 9/2/2025 Partial Approval CHRISTOPHER ROJAS
HVAC-Final 9/2/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 9/2/2025 Approved CHRISTOPHER ROJAS
Smoke Detectors 9/2/2025 Approved CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 9/3/2025 Conditional Approval RAUL OLAGI
Final 9/3/2025 OK to Issue CofO CHRISTOPHER ROJAS