11154 N HASKELL AVE 91344

Certificate Information: 11154 N HASKELL AVE 91344

Application / Permit
24014-20000-04806
Plan Check / Job No.
B24VN21138
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 11/1/2024 JESSE ARELLANO
Corrections Issued 11/2/2024 JESSE ARELLANO
Building Plans Picked Up 1/16/2025 APPLICANT
Plan Check Approved 3/12/2025 SERGIO MUNIZ
Issued 3/12/2025 APPLICANT
CofO in Progress 8/14/2025 JENNIFER RABUCHIN
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/12/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 2/12/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 2/12/2025 XOCHITL ARQUIETA
Grading Pre-Inspection Cleared 2/21/2025 ROBERT PINA
Sewer availability Cleared 2/21/2025 XOCHITL ARQUIETA
Construction near power lines Cleared 3/7/2025 THERESA NGUYEN

Contact Information

Contractor Ease-Build Inc; Lic. No.: 1087958-B 5339 NEWCASTLE AVE #104      ENCINO, CA 91316

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/18/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 3/19/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/19/2025 Partial Approval JENNIFER RABUCHIN
Sewer 3/19/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/3/2025 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Approval JACK KARGODORIAN
Green Building Rough 4/3/2025 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 4/3/2025 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 4/17/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/17/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/17/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 4/17/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 4/17/2025 Approved JENNIFER RABUCHIN
Deputy Wood Construction 4/18/2025 Conditional Approval RAUL OLAGI
Insulation 4/21/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 4/21/2025 Partial Approval JENNIFER RABUCHIN
Shower Pan 4/21/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 4/28/2025 Approved JENNIFER RABUCHIN
Insulation 4/28/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/21/2025 Partial Approval JENNIFER RABUCHIN
Final 7/21/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/21/2025 Approved JENNIFER RABUCHIN
Green Building Final 7/21/2025 Approved JENNIFER RABUCHIN
Green Building Rough 7/21/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/21/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/21/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/24/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/24/2025 Approved JENNIFER RABUCHIN
Final 7/24/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 7/24/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/24/2025 Approved JENNIFER RABUCHIN
Final 8/14/2025 OK to Issue CofO JENNIFER RABUCHIN