11154 N HASKELL AVE 91344
Certificate Information: 11154 N HASKELL AVE 91344
- Application / Permit
- 24014-20000-04806
- Plan Check / Job No.
- B24VN21138
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 3/12/2025
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | JESSE ARELLANO |
| Corrections Issued | 11/2/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 1/16/2025 | APPLICANT |
| Plan Check Approved | 3/12/2025 | SERGIO MUNIZ |
| Issued | 3/12/2025 | APPLICANT |
| CofO in Progress | 8/14/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/12/2025 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2025 | XOCHITL ARQUIETA |
| Roof/Waste drainage to street | Cleared | 2/12/2025 | XOCHITL ARQUIETA |
| Grading Pre-Inspection | Cleared | 2/21/2025 | ROBERT PINA |
| Sewer availability | Cleared | 2/21/2025 | XOCHITL ARQUIETA |
| Construction near power lines | Cleared | 3/7/2025 | THERESA NGUYEN |
Contact Information
| Contractor | Ease-Build Inc; Lic. No.: 1087958-B | 5339 NEWCASTLE AVE #104 ENCINO, CA 91316 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/18/2025 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 3/19/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/19/2025 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 3/19/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/3/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 4/3/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 4/3/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/17/2025 | Approved | JENNIFER RABUCHIN |
| Deputy Wood Construction | 4/18/2025 | Conditional Approval | RAUL OLAGI |
| Insulation | 4/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/21/2025 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 4/21/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 4/28/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/28/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/21/2025 | Partial Approval | JENNIFER RABUCHIN |
| Final | 7/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/21/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 7/21/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/21/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/21/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/21/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/24/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 7/24/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/24/2025 | Approved | JENNIFER RABUCHIN |
| Final | 8/14/2025 | OK to Issue CofO | JENNIFER RABUCHIN |