12537 W DEBELL ST 91331

Certificate Information: 12537 W DEBELL ST 91331

Application / Permit
24014-20000-04804
Plan Check / Job No.
B24VN21103
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
33'-0" X 33'-7" ADDITION TO (E) SFD PER WFPP. NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 11/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 11/1/2024 ARTIN ZARUKIAN
Corrections Issued 11/2/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/5/2024 APPLICANT
Plan Check Approved 11/15/2024 ISIS ARGUETA
Issued 11/20/2024 APPLICANT
CofO in Progress 12/4/2025 MICHEL ABAJAN
Permit Finaled 12/18/2025 RUBEN SALAS
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/7/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/7/2024 CARLOS AGUILERA
Sewer availability Cleared 11/7/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/18/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/21/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/28/2025 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 3/28/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 6/18/2025 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 6/18/2025 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 6/23/2025 Approved MICHEL ABAJAN
HVAC-Rough 6/23/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 6/23/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/25/2025 Approved MICHEL ABAJAN
Green Building Rough 6/25/2025 Approved MICHEL ABAJAN
Insulation 6/27/2025 Approved MICHEL ABAJAN
Drywall Nailing 8/11/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/11/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 12/2/2025 Approved MICHEL ABAJAN
Final 12/2/2025 OK to Issue CofO MICHEL ABAJAN
Green Building Final 12/2/2025 Approved MICHEL ABAJAN
HVAC-Final 12/2/2025 Approved MICHEL ABAJAN
PLUMBING-Final 12/2/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/2/2025 Approved MICHEL ABAJAN