4643-4645 W VANTAGE AVE 91607

Certificate Information: 4643-4645 W VANTAGE AVE 91607

Application / Permit
24014-20000-04796
Plan Check / Job No.
B24VN21048
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
25'-6" X 14'-6" ACCESSORY DWELLING ADDITION TO (E) SFD PER LAMC 12.22 A.33(c) and (e).
Permit Issued
Issued on 1/28/2025
Issuing Office
Valley
Current Status
Issued on 1/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/25/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 ARTIN ZARUKIAN
Corrections Issued 11/4/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/4/2024 APPLICANT
Plan Check Approved 1/24/2025 ALEC MOUSAKHANIAN
Issued 1/28/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/12/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/12/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/19/2024 CARLOS AGUILERA
Sewer availability Cleared 11/19/2024 CARLOS AGUILERA
Specific Plan Cleared 11/19/2024 JOANNA MARROQUIN
Construction near power lines Cleared 1/8/2025 RIDWAN HARDY

Contact Information

Contractor Riniker Joe Construction; Lic. No.: 665674-B 4653 VANTAGE AVENUE      VALLEY VILLAGE, CA 91607
Engineer Banda,, Peter Hector; Lic. No.: C31433 1930 W GLENOAKS BLVD STE 07      GLENDALE, CA 91201

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/17/2025 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 4/1/2025 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 4/3/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/18/2025 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/18/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/18/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 8/18/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Rough 8/18/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/18/2025 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 8/21/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/25/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 8/25/2025 Approved CHRISTOPHE COCHRAN
Wood Frame 8/25/2025 Approved CHRISTOPHE COCHRAN
Insulation 9/12/2025 Approved CHRISTOPHE COCHRAN
Sewer 9/12/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Shower Pan 9/12/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Drywall Nailing 9/17/2025 Approved CHRISTOPHE COCHRAN
Sewer 9/17/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 9/17/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/26/2025 Approved CHRISTOPHER MORFIN
Special/Order Compliance 9/26/2025 Partial Inspection JUAN VALENZUELA
Final 5/21/2026 Conditional Approval CHRISTOPHE COCHRAN
Green Building Final 5/21/2026 Approved CHRISTOPHE COCHRAN
MERV13>=Final 5/21/2026 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/21/2026 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 5/21/2026 Approved CHRISTOPHE COCHRAN