9643-9645 N LANGDON AVE 91343
Certificate Information: 9643-9645 N LANGDON AVE 91343
- Application / Permit
- 24014-20000-04770
- Plan Check / Job No.
- B24VN20909
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: CONVERT (E) ATTACHED GARAGE TO ADU W/ ADDITION PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 2/17/2025
- Issuing Office
- Current Status
- CofO Issued on 10/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 11/1/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 1/13/2025 | DANIEL SANJUAN |
| Plan Check Approved | 2/6/2025 | JOSE VELAZQUEZ |
| Issued | 2/17/2025 | APPLICANT |
| CofO in Progress | 10/6/2025 | VINCENT HANLEY |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
| CofO Issued | 10/28/2025 | RUBEN SALAS |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 12/30/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/23/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/9/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/22/2025 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/22/2025 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 4/29/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 4/30/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/30/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/10/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/10/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/10/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/3/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/3/2025 | Approved | VINCENT HANLEY |
| Insulation | 7/3/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/3/2025 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 7/3/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/8/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/23/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 9/23/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 9/23/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/23/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 9/23/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/23/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/23/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 10/6/2025 | Approved | VINCENT HANLEY |
| Final | 10/6/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 10/6/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 10/6/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 10/6/2025 | Approved | VINCENT HANLEY |