11002 N BORDEN AVE 91331
Certificate Information: 11002 N BORDEN AVE 91331
- Application / Permit
- 24014-20000-04753
- Plan Check / Job No.
- B24VN20825
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) PATIO COVER (126 SF) AND ADD 9' X 21'-6" (165 SF) STUDY ROOM AND BATHROOM TO THE (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 11/1/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/7/2024 | APPLICANT |
| Applicant returned to address corrections | 2/4/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 2/7/2025 | GIOVANNY CHAVEZ |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 8/13/2025 | MICHEL ABAJAN |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/12/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 1/2/2025 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2025 | RYAN CASTRO |
Contact Information
| Contractor | Sam Jr Construction; Lic. No.: 752569-B | 11924 EDGECLIFF AVENUE SYLMAR, CA 91342 |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/21/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/21/2025 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/26/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/26/2025 | Partial Approval | MICHEL ABAJAN |
| Deputy Reinf. Concrete | 3/28/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/2/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 5/2/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/7/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/7/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/16/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/16/2025 | Approved | MICHEL ABAJAN |
| Insulation | 5/23/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/23/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/17/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/14/2025 | Approved | MICHEL ABAJAN |
| Final | 7/14/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/14/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/14/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/14/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 7/14/2025 | Approved | MICHEL ABAJAN |
| Final | 8/12/2025 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Approved | MICHEL ABAJAN |